8054 W LE BERTHON ST 91040
Certificate Information: 8054 W LE BERTHON ST 91040
- Application / Permit
- 21014-20000-02320
- Plan Check / Job No.
- B21VN05635
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 14'-1" X 17'-9" IRREGULAR SHAPED ADDITION AT FRONT AND 9'-10" X 22'-3" ADDITION AT REAR AND REMODEL (E) SFD. ADD 14'-6" X 17'-9" TRELLIS PATIO COVER AT REAR. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/12/2021
- Issuing Office
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2021 | RAPHAEL ROSAS |
| Corrections Issued | 5/15/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/22/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 10/26/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 10/28/2021 | APPLICANT |
| Issued | 11/12/2021 | APPLICANT |
| CofO in Progress | 3/26/2024 | WILLIAM WREN |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
| CofO Issued | 4/2/2024 | RUBEN SALAS |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/25/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/25/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/25/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 6/8/2021 | KIRK LINKLATER |
| Tract Map conditions | Cleared | 7/19/2021 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/7/2021 | Partial Approval | MATTHEW NELSON |
| Sewer | 12/7/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 12/10/2021 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 12/21/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/30/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Partial Approval | MATTHEW NELSON |
| HVAC-Rough | 3/30/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/30/2022 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/4/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 4/4/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/4/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 4/6/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/11/2022 | Corrections Issued | WILLIAM WREN |
| Insulation | 4/13/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/13/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/20/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/20/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 4/20/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/2/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/9/2024 | Approved | WILLIAM WREN |
| Final | 2/9/2024 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 2/9/2024 | Approved | WILLIAM WREN |
| Green Building Final | 2/9/2024 | Corrections Issued | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 2/9/2024 | Approved | WILLIAM WREN |
| Verify Sprinkler Sign Off | 2/9/2024 | Approved | WILLIAM WREN |
| Final | 2/13/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 2/13/2024 | Approved | WILLIAM WREN |
| Final | 2/20/2024 | OK to Issue CofO | WILLIAM WREN |
| Final | 3/4/2024 | Corrections Issued | WILLIAM WREN |
| Final | 3/21/2024 | Not Ready for Inspection | WILLIAM WREN |