8054 W LE BERTHON ST 91040

Certificate Information: 8054 W LE BERTHON ST 91040

Application / Permit
21014-20000-02320
Plan Check / Job No.
B21VN05635
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 14'-1" X 17'-9" IRREGULAR SHAPED ADDITION AT FRONT AND 9'-10" X 22'-3" ADDITION AT REAR AND REMODEL (E) SFD. ADD 14'-6" X 17'-9" TRELLIS PATIO COVER AT REAR. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/12/2021
Issuing Office
Current Status
CofO Issued on 4/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2021 APPLICANT
Assigned to Plan Check Engineer 5/14/2021 RAPHAEL ROSAS
Corrections Issued 5/15/2021 RAPHAEL ROSAS
Applicant returned to address corrections 9/22/2021 RAPHAEL ROSAS
Plan Check Approved 10/26/2021 RAPHAEL ROSAS
Building Plans Picked Up 10/28/2021 APPLICANT
Issued 11/12/2021 APPLICANT
CofO in Progress 3/26/2024 WILLIAM WREN
Permit Finaled 4/2/2024 RUBEN SALAS
CofO Issued 4/2/2024 RUBEN SALAS
Permit Finaled 4/2/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/25/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/25/2021 CARLOS AGUILERA
Sewer availability Cleared 5/25/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/26/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 6/8/2021 KIRK LINKLATER
Tract Map conditions Cleared 7/19/2021 PABLO ESTRADA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/7/2021 Partial Approval MATTHEW NELSON
Sewer 12/7/2021 Not Ready for Inspection MATTHEW NELSON
Deputy Drilled-In Anchors 12/10/2021 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 12/21/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 3/30/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Partial Approval MATTHEW NELSON
HVAC-Rough 3/30/2022 Approved MATTHEW NELSON
PLUMBING-Rough 3/30/2022 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 4/4/2022 Corrections Issued MATTHEW NELSON
Green Building Rough 4/4/2022 Approved MATTHEW NELSON
PLUMBING-Rough 4/4/2022 Approved MATTHEW NELSON
Wood Frame 4/6/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/11/2022 Corrections Issued WILLIAM WREN
Insulation 4/13/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/13/2022 Approved MATTHEW NELSON
Drywall Nailing 4/20/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/20/2022 Approved MATTHEW NELSON
Shower Pan 4/20/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 5/2/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 2/9/2024 Approved WILLIAM WREN
Final 2/9/2024 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 2/9/2024 Approved WILLIAM WREN
Green Building Final 2/9/2024 Corrections Issued WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 2/9/2024 SGSOV Approved WILLIAM WREN
Smoke Detectors 2/9/2024 Approved WILLIAM WREN
Verify Sprinkler Sign Off 2/9/2024 Approved WILLIAM WREN
Final 2/13/2024 Corrections Issued WILLIAM WREN
Green Building Final 2/13/2024 Approved WILLIAM WREN
Final 2/20/2024 OK to Issue CofO WILLIAM WREN
Final 3/4/2024 Corrections Issued WILLIAM WREN
Final 3/21/2024 Not Ready for Inspection WILLIAM WREN