3826 S MCLAUGHLIN AVE 90066

Certificate Information: 3826 S MCLAUGHLIN AVE 90066

Application / Permit
21014-20000-02280
Plan Check / Job No.
B21VN05582
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
18' X 12'-6" ADDITION OF A FAMILY ROOM AT THE FIRST FLOOR OF THE (E) TWO STORY SINGLE FAMILY DWELLING. REPLACE WINDOWS AND DOORS AT THE FIRST AND SECOND FLOOR.
Permit Issued
Issued on 6/17/2021
Issuing Office
Current Status
CofO Issued on 3/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 SERGIO MUNIZ
Corrections Issued 5/15/2021 SERGIO MUNIZ
Plan Check Approved 6/14/2021 SERGIO MUNIZ
Issued 6/17/2021 APPLICANT
Building Plans Picked Up 6/18/2021 APPLICANT
CofO in Progress 3/7/2022 DAVID FEILER
Permit Finaled 3/10/2022 DANIEL ORRANTE
CofO Issued 3/10/2022 DANIEL ORRANTE
Permit Finaled 3/10/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 6/2/2021 KEVIN ARUCAN
Roof/Waste drainage to street Cleared 6/3/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/4/2021 DINAH GARIN

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Litman Inc; Lic. No.: 891510-B 19528 VENTURA BLVD   UNIT 242    TARZANA, CA 91356

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/2/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/20/2021 Approved ENRIQUE MIRELES
Deputy Wood Construction 11/5/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/9/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/9/2021 Approved ENRIQUE MIRELES
Green Building Rough 11/9/2021 Approved ENRIQUE MIRELES
HVAC-Rough 11/9/2021 Approved ENRIQUE MIRELES
Insulation 11/15/2021 Approved JOHN KAYON
Interior/Exterior Lathing 11/15/2021 Approved JOHN KAYON
Drywall Nailing 11/18/2021 Approved JOHN KAYON
Final 1/26/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 1/26/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 1/26/2022 Approved ENRIQUE MIRELES
Final 2/23/2022 Corrections Issued ENRIQUE MIRELES
Final 3/7/2022 OK to Issue CofO DAVID FEILER