11627 W WIXOM ST 91605
Certificate Information: 11627 W WIXOM ST 91605
- Application / Permit
- 21014-20000-02246
- Plan Check / Job No.
- B21VN05524
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 17'-0" X 9'-0" (IRREGULAR SHAPED) ADDITION AND FIRE DAMAGE REPAIR TO (E) SFD.
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 5/8/2021 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 1/11/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 1/25/2022 | ARTIN ZARUKIAN |
| Issued | 1/25/2022 | APPLICANT |
| Building Plans Picked Up | 1/26/2022 | APPLICANT |
| CofO in Progress | 4/22/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
| CofO Issued | 6/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/26/2021 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/1/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Vicsinc.Com; Lic. No.: 1002544-B | P O BOX 950931 MISSION HILLS, CA 91395 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/26/2022 | No Result Entered | ADRIAN GAUTHIER |
| Footing/Foundation/Slab | 1/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 1/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 1/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 1/31/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 1/31/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 1/31/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 1/31/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/31/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Sewer | 1/31/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Wood Frame | 1/31/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/2/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 2/2/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 2/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/4/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 2/4/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 2/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 2/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 2/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/2/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 3/2/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 3/2/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 3/2/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 3/2/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 3/2/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 3/7/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 3/7/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 3/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/18/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 3/18/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 3/18/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 3/18/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 3/18/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 3/18/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 4/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 4/5/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 4/5/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 4/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 4/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Gas Test | 4/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 4/11/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 4/22/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |