5813 N CEDROS AVE 91411
Certificate Information: 5813 N CEDROS AVE 91411
- Application / Permit
- 21014-20000-02245
- Plan Check / Job No.
- B21VN05519
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 18'-6" X 24'-9"ADDITION OF A MASTER BEDROOM, BATHROOM AND CLOSET AND REMODEL BEDROOM TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 7/28/2021
- Issuing Office
- Current Status
- CofO Issued on 5/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | SERGIO MUNIZ |
| Corrections Issued | 5/15/2021 | SERGIO MUNIZ |
| Plan Check Approved | 6/2/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 6/30/2021 | APPLICANT |
| Issued | 7/28/2021 | APPLICANT |
| CofO in Progress | 5/19/2022 | RICHARD DOCKUS |
| Permit Finaled | 5/25/2022 | MICHAEL SMITH |
| CofO Issued | 5/25/2022 | MICHAEL SMITH |
| Permit Finaled | 5/25/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 5/21/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/21/2021 | GABRIEL ROBLES |
Contact Information
| Architect | , ; Lic. No.: C33595 | 17977 MILLER AVENUE FONTANA, CA 92336 |
| Contractor | United Firm Construction Inc; Lic. No.: 400062-B | 1568 LOMA VISTA ST PASADENA, CA 91104 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/10/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 12/21/2021 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 12/21/2021 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2021 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/9/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 2/9/2022 | Approved | RICHARD DOCKUS |
| Rough-Elec/Plmb/HVAC | 2/9/2022 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 2/14/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/14/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 2/14/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/14/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 2/24/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/24/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 2/28/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 5/12/2022 | Approved | RICHARD DOCKUS |
| Final | 5/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 5/12/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 5/12/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 5/12/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 5/12/2022 | Corrections Issued | RICHARD DOCKUS |
| Final | 5/16/2022 | Partial Inspection | ROBERT GOLD |
| Smoke Detectors | 5/16/2022 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 5/19/2022 | Approved | RICHARD DOCKUS |
| Final | 5/19/2022 | OK to Issue CofO | RICHARD DOCKUS |