10841 W WRIGHTWOOD LANE 91604
Certificate Information: 10841 W WRIGHTWOOD LANE 91604
- Application / Permit
- 21014-20000-02213
- Plan Check / Job No.
- B21VN05415
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR REMODEL AND IRREGULAR SHAPED 407 SQFT ADDITION TO (E) SFD, W/NEW ATTACHED OPEN TRELLIS AT REAR (21'-0"x10'-9") W/NFPA 13D SPRINKLERS THROUGHOUT SEE COMMENTS.
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- Issued on 12/2/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | PETER MOSESIAN |
| Corrections Issued | 6/5/2021 | PETER MOSESIAN |
| Quality Review Completed | 6/14/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/15/2021 | APPLICANT |
| Plan Check Approved | 12/1/2021 | PETER MOSESIAN |
| Issued | 12/2/2021 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 7/1/2021 | OLGA AYALA |
| ZI | Cleared | 7/9/2021 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 10/22/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 10/26/2021 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 11/15/2021 | PETER MOSESIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Durand,, Paul Henri; Lic. No.: S4222 | 611 N G ST OXNARD, CA 93030 |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 1/26/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 2/14/2022 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 2/14/2022 | Approved | BRIAN SULLIVAN |
| Underground Mechanical | 2/14/2022 | Approved | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 2/15/2022 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 5/25/2022 | Conditional Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 11/10/2022 | No Access for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 11/10/2022 | No Access for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 11/10/2022 | No Access for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 11/10/2022 | No Access for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 11/10/2022 | No Access for Inspection | BRIAN SULLIVAN |
| Special/Order Compliance | 11/10/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 11/10/2022 | No Access for Inspection | BRIAN SULLIVAN |
| Green Building Final | 11/15/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 11/17/2022 | Corrections Issued | BRIAN SULLIVAN |
| Special/Order Compliance | 12/2/2022 | Partial Inspection | BRIAN SULLIVAN |
| Special/Order Compliance | 1/24/2023 | Partial Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 3/8/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 3/8/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/8/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 3/8/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 3/8/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/28/2023 | Partial Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 4/28/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Partial Inspection | BRIAN SULLIVAN |
| Green Building Rough | 4/28/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 4/28/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/28/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 4/28/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 4/28/2023 | Partial Inspection | BRIAN SULLIVAN |
| Special/Order Compliance | 7/5/2024 | Partial Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/22/2025 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/1/2025 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 7/1/2025 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 7/1/2025 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 2/23/2026 | Partial Approval | DAVID WILLIAMS |
| Drywall Nailing | 3/26/2026 | Approved | ROY SPAULDING |
| Final | 3/26/2026 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 3/26/2026 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 3/26/2026 | Approved | ROY SPAULDING |
| Final | 4/2/2026 | Order to Comply Issued | ROY SPAULDING |