4303 N ELMER AVE 91602

Certificate Information: 4303 N ELMER AVE 91602

Application / Permit
21014-20000-02207
Plan Check / Job No.
B21VN05402
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (28'-5" x 13'-11"), 391 SQFT AND (11'-11"x4'-11"),62 SQFT TO REAR OF SFDW/ INT. , NEW 156 SQFT FRONT PORCH, REMODEL AND NEW (28'-5"x10'-7"),255 SQFT OPEN TRELLIS TO (E) SFD
Permit Issued
Issued on 12/14/2021
Issuing Office
Current Status
CofO Issued on 2/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 PETER MOSESIAN
Corrections Issued 6/9/2021 PETER MOSESIAN
Quality Review Completed 6/23/2021 OMID HEDAYAT
Plan Check Approved 12/9/2021 PETER MOSESIAN
Issued 12/14/2021 APPLICANT
CofO in Progress 1/10/2023 JACK KARGODORIAN
CofO in Progress 1/12/2023 JACK KARGODORIAN
Permit Finaled 2/7/2023 MICHAEL SMITH
CofO Issued 2/7/2023 MICHAEL SMITH
Permit Finaled 2/7/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/26/2021 CARLOS AGUILERA
ZI Cleared 7/29/2021 ANACANY HURTADO
Construction near power lines Cleared 9/13/2021 RIDWAN HARDY
Low Impact Development Cleared 11/12/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 11/17/2021 CARLOS AGUILERA
Sewer availability Cleared 11/18/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/10/2022 Approved CALEB MEISTER
Excavation/Setback/Form/Re-Bar 1/19/2022 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 1/31/2022 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 2/22/2022 Corrections Issued THOMAS FINNILA
Green Building Rough 2/22/2022 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 2/28/2022 Partial Approval THOMAS FINNILA
Deputy Drilled-In Anchors 3/2/2022 Conditional Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/29/2022 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 4/14/2022 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 4/14/2022 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 4/14/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 4/14/2022 Corrections Issued THOMAS FINNILA
Deputy Wood Construction 4/15/2022 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 4/19/2022 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Partial Inspection THOMAS FINNILA
ELECTRICAL-Rough 4/26/2022 Conditional Approval DAVID MATSON
HVAC-Rough 4/26/2022 Partial Approval DAVID MATSON
PLUMBING-Rough 4/26/2022 Approved DAVID MATSON
Wood Frame 4/26/2022 Approved DAVID MATSON
Footing/Foundation/Slab 4/28/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 4/28/2022 Partial Approval THOMAS FINNILA
Insulation 5/5/2022 Approved DAVID MATSON
Drywall Nailing 5/12/2022 Approved DAVID MATSON
Green Building Rough 5/12/2022 Approved DAVID MATSON
Interior/Exterior Lathing 5/12/2022 Not Ready for Inspection DAVID MATSON
Shower Pan 5/12/2022 Not Ready for Inspection DAVID MATSON
Interior/Exterior Lathing 5/17/2022 Not Ready for Inspection DAVID MATSON
Shower Pan 5/17/2022 Not Ready for Inspection DAVID MATSON
Interior/Exterior Lathing 5/23/2022 Partial Approval THOMAS FINNILA
Shower Pan 5/23/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 5/31/2022 Approved WILLIAM WREN
ELECTRICAL-Final 10/4/2022 Corrections Issued THOMAS FINNILA
Service/Power Release 10/4/2022 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 11/4/2022 Approved JACK KARGODORIAN
ELECTRICAL-Final 11/4/2022 Not Ready for Inspection JACK KARGODORIAN
Final 11/4/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 11/4/2022 Approved JACK KARGODORIAN
HVAC-Final 11/4/2022 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Final 11/4/2022 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 11/4/2022 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 11/4/2022 Approved JACK KARGODORIAN
ELECTRICAL-Final 12/1/2022 Approved JOHN COLEMAN
HVAC-Final 12/1/2022 Approved JOHN COLEMAN
PLUMBING-Final 12/1/2022 Approved JOHN COLEMAN
Final 1/9/2023 OK to Issue CofO JACK KARGODORIAN
Final 1/11/2023 OK to Issue CofO JACK KARGODORIAN