11580-11582 N WHEELER AVE 91342

Certificate Information: 11580-11582 N WHEELER AVE 91342

Application / Permit
21014-20000-02200
Plan Check / Job No.
B21VN05381
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMODELING THE KITCHEN IN (E) SFD; CONVERT THE (E) 21'-9" X 22'-3" ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CGS 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 9/19/2021
Issuing Office
Current Status
CofO Issued on 10/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2021 APPLICANT
Assigned to Plan Check Engineer 5/7/2021 PARISA ZAHABI
Corrections Issued 5/8/2021 PARISA ZAHABI
Applicant returned to address corrections 6/2/2021 PARISA ZAHABI
Applicant returned to address corrections 6/16/2021 PARISA ZAHABI
Applicant returned to address corrections 7/19/2021 PARISA ZAHABI
Applicant returned to address corrections 8/4/2021 PARISA ZAHABI
Plan Check Approved 8/25/2021 PARISA ZAHABI
Building Plans Picked Up 9/1/2021 APPLICANT
Issued 9/19/2021 APPLICANT
CofO in Progress 9/30/2022 MICHEL ABAJAN
Permit Finaled 10/6/2022 DANIEL ORRANTE
CofO Issued 10/6/2022 DANIEL ORRANTE
Permit Finaled 10/6/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/17/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 5/17/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/20/2021 GABRIEL ROBLES
Sewer availability Cleared 5/20/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 8/25/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/17/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/25/2022 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Final 3/25/2022 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Partial Approval MICHEL ABAJAN
Gas Test 3/25/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 3/25/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/26/2022 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Rough 4/26/2022 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/26/2022 Partial Approval MICHEL ABAJAN
HVAC-Rough 4/26/2022 Partial Inspection MICHEL ABAJAN
Insulation 4/26/2022 Partial Inspection MICHEL ABAJAN
Reinforced Masonry Frame 4/26/2022 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 4/29/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/29/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Partial Approval MICHEL ABAJAN
HVAC-Rough 4/29/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/27/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 Partial Approval MICHEL ABAJAN
Insulation 5/27/2022 Approved MICHEL ABAJAN
Reinforced Masonry Frame 5/27/2022 Partial Inspection MICHEL ABAJAN
Drywall Nailing 6/17/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 9/16/2022 Corrections Issued JENNIFER RABUCHIN
Final 9/16/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 9/16/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 9/16/2022 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 9/30/2022 Approved MICHEL ABAJAN
Final 9/30/2022 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 9/30/2022 Approved MICHEL ABAJAN
PLUMBING-Final 9/30/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/30/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 9/30/2022 Approved MICHEL ABAJAN