3318 S COOLIDGE AVE 90066
Certificate Information: 3318 S COOLIDGE AVE 90066
- Application / Permit
- 21014-20000-02197
- Plan Check / Job No.
- B21VN05373
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2'-8.5" x 3'-3.4" ADDITION TO 1ST FLR AND 14' x 32' 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELLING, AND MAJOR REMODEL; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 2/14/2022
- Issuing Office
- Current Status
- CofO Issued on 1/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | SEAN SHAHMIRI |
| Corrections Issued | 6/10/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 6/10/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/11/2021 | APPLICANT |
| Applicant returned to address corrections | 1/25/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 1/27/2022 | SEAN SHAHMIRI |
| Issued | 2/14/2022 | APPLICANT |
| CofO in Progress | 1/3/2024 | JESUS PINEDA |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
| CofO Issued | 1/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | TRACY TATE |
| Miscellaneous | Cleared | 10/20/2021 | PEDRO AYALA |
| Low Impact Development | Cleared | 12/17/2021 | LONDY ALVARADO |
| Grading Pre-Inspection | Cleared | 12/28/2021 | SEAN SHAHMIRI |
| Roof/Waste drainage to street | Cleared | 1/6/2022 | DINAH GARIN |
| Sewer availability | Cleared | 1/12/2022 | DINAH GARIN |
Contact Information
| Contractor | Alright Already; Lic. No.: 789174-B | 17261 SUNBURST STREET NORTHRIDGE, CA 91325 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/4/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/11/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 5/9/2022 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 5/9/2022 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 5/12/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Corrections Issued | HERBERT GIRON |
| Deputy Wood Construction | 10/24/2022 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 11/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 11/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 11/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 11/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Pre-Inspection | 11/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 1/25/2023 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 1/25/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/25/2023 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 2/13/2023 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 2/13/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 2/13/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 2/13/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 2/13/2023 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 2/13/2023 | Approved | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 2/13/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 2/22/2023 | Approved | JOHNNY MIRANDA |
| Shower Pan | 2/22/2023 | Corrections Issued | JOHNNY MIRANDA |
| Drywall Nailing | 2/28/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 2/28/2023 | Approved | JOHNNY MIRANDA |
| Shower Pan | 2/28/2023 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 9/21/2023 | Approved | JESUS PINEDA |
| HVAC-Final | 9/21/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 9/21/2023 | Approved | JESUS PINEDA |
| Final | 12/21/2023 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 12/21/2023 | Approved | JESUS PINEDA |
| Green Building Final | 12/21/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 12/21/2023 | Approved | JESUS PINEDA |
| Final | 1/3/2024 | OK to Issue CofO | JESUS PINEDA |