2027 N GLENCOE WAY 90068

Certificate Information: 2027 N GLENCOE WAY 90068

Application / Permit
21014-20000-02188
Plan Check / Job No.
B21VN05350
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 20'5-1/2"X40'7-1/2" LOWER STORAGE LEVEL TO HABITABLE AREA AND ADD INTERIOR STAIRS
Permit Issued
Issued on 11/8/2021
Issuing Office
Metro
Current Status
Permit Finaled on 4/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 MARVEL DELACRUZ
Corrections Issued 6/17/2021 MARVEL DELACRUZ
Quality Review Completed 6/28/2021 STEVEN KIM
Applicant returned to address corrections 8/18/2021 MARVEL DELACRUZ
Plan Check Approved 10/20/2021 MARVEL DELACRUZ
Issued 11/8/2021 APPLICANT
Permit Finaled 4/25/2022 BRIAN SULLIVAN

Permit Application Clearance Information

Sewer availability Cleared 7/19/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/20/2021 JEANIE LAM
Miscellaneous Cleared 7/27/2021 LAUREN PADICK
Grading Pre-Inspection Cleared 8/3/2021 BRIAN MILLER
GPI Written Notices Cleared 10/20/2021 MARVEL DELACRUZ
Green Code Cleared 10/20/2021 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/22/2021 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 1/4/2022 Conditional Approval BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 1/4/2022 Approved BRIAN SULLIVAN
Special/Order Compliance 1/4/2022 Corrections Issued BRIAN SULLIVAN
Insulation 1/13/2022 Approved BRIAN SULLIVAN
Drywall Nailing 2/8/2022 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 3/2/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 3/14/2022 Partial Approval BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 4/22/2022 SGSOV Not Ready BRIAN SULLIVAN
Final 4/25/2022 Permit Finaled BRIAN SULLIVAN
Green Building Final 4/25/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 4/25/2022 Approved BRIAN SULLIVAN