11615 N LOUISE AVE 91344

Certificate Information: 11615 N LOUISE AVE 91344

Application / Permit
21014-20000-02176
Plan Check / Job No.
B21VN05309
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20-6"' X 21'-6" ATTACHED GARAGE TO A (N) DEN AND ADD 20'-9" X 29'-9" FOR NEW BEDROOM/FULLBATH/CLOSET AND REMODEL BATHROOMS/CLOSET AT SECOND FLOOR FOR (E) 2-STORY SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/4/2022
Issuing Office
Current Status
CofO Issued on 11/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 JENNIFER LEE
Corrections Issued 5/10/2021 JENNIFER LEE
Applicant returned to address corrections 1/14/2022 RAPHAEL ROSAS
Plan Check Approved 1/31/2022 RAPHAEL ROSAS
Building Plans Picked Up 2/2/2022 APPLICANT
Issued 3/4/2022 APPLICANT
CofO in Progress 8/27/2024 STEVEN BACK
No Progress 8/30/2024 STEVEN BACK
CofO in Progress 8/30/2024 STEVEN BACK
CofO in Progress 8/30/2024 SEAN WIRCH
CofO in Progress 11/20/2024 STEVEN BACK
CofO Issued 11/25/2024 JOHN JANSON
Permit Finaled 11/25/2024 JOHN JANSON

Permit Application Clearance Information

Sewer availability Cleared 5/18/2021 ADRIAN CASTRO
Low Impact Development Cleared 12/15/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/20/2021 AMIR KASHFI
Grading Pre-Inspection Cleared 3/1/2022 JENNIFER LEE
Eng Process Fee Ord 176,300 Cleared 3/2/2022 AMIR KASHFI

Contact Information

Architect Gold,, Kerry Daniel; Lic. No.: C13781 638 LINDERO CYN RD # 432      OAK PARK, CA 91377
Contractor Owner-Builder       ,
Engineer Sayah,, Daniel Hoshyar; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/5/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 12/5/2022 Partial Approval STEVEN BACK
Green Building Rough 12/5/2022 Not Ready for Inspection STEVEN BACK
HVAC-Rough 12/5/2022 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 12/5/2022 Partial Approval STEVEN BACK
Pre-Inspection 1/6/2023 Partial Approval STEVEN BACK
Wood Frame 1/6/2023 Partial Approval STEVEN BACK
Pre-Inspection 1/27/2023 Partial Inspection STEVEN BACK
Special/Order Compliance 1/27/2023 Partial Inspection MORRIS JACKSON
Deputy Drilled-In Anchors 4/11/2023 Conditional Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 4/13/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 4/13/2023 Approved SEAN HAUPT
Green Building Rough 4/25/2023 Not Ready for Inspection HORACE FULTZ
Underground Mechanical 4/25/2023 Approved HORACE FULTZ
Wood Frame 4/27/2023 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 7/3/2023 Approved STEVEN BACK
ELECTRICAL-Rough 7/3/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Approved STEVEN BACK
Green Building Rough 7/3/2023 Approved STEVEN BACK
HVAC-Rough 7/3/2023 Approved STEVEN BACK
Interior/Exterior Lathing 7/3/2023 Partial Approval STEVEN BACK
PLUMBING-Rough 7/3/2023 Approved STEVEN BACK
Insulation 7/10/2023 Approved STEVEN BACK
Drywall Nailing 7/13/2023 Approved STEVEN BACK
Shower Pan 7/24/2023 Approved HENRY KIM
Interior/Exterior Lathing 7/26/2023 Approved STEVEN BACK
Final 10/25/2023 Corrections Issued STEVEN BACK
Green Building Final 10/25/2023 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/25/2023 SGSOV Approved STEVEN BACK
Smoke Detectors 10/25/2023 Approved STEVEN BACK
Final 8/27/2024 Corrections Issued STEVEN BACK
Deputy Wood Construction 8/30/2024 Approved STEVEN BACK
Special/Order Compliance 8/30/2024 Corrections Issued STEVEN BACK
Pre-Inspection 10/17/2024 Partial Inspection STEVEN BACK
Final 11/20/2024 OK to Issue CofO STEVEN BACK