5116 N OTSEGO CT 91436
Certificate Information: 5116 N OTSEGO CT 91436
- Application / Permit
- 21014-20000-02161
- Plan Check / Job No.
- B21VN05276
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION (34'-3" x 35'-10"),1181 SQFT AND NEW 1 STORY ADDITION 214 SQFT, TO (E) 1 STORY SFD, MAJOR REMODEL, (N) COVERED PERGOLA (28'-3" x 10'-0") AT REAR, W/ BALCONY ABOVE, NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/29/2021
- Issuing Office
- Current Status
- Issued on 11/29/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | PETER MOSESIAN |
| Corrections Issued | 5/22/2021 | PETER MOSESIAN |
| Quality Review Completed | 5/25/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 5/26/2021 | APPLICANT |
| Plan Check Approved | 11/19/2021 | PETER MOSESIAN |
| Issued | 11/29/2021 | APPLICANT |
Permit Application Clearance Information
| Watercourse | Cleared | 5/26/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/8/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 7/23/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 8/24/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/5/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 11/8/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manlangit,, Vicente Balingasa; Lic. No.: C75499 | 7919 SAUSALITO AVE WEST HILLS, CA 91304 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/2/2022 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/19/2022 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 5/19/2022 | Partial Inspection | DAVID SANDOVAL |
| Green Building Rough | 5/19/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Deputy Wood Construction | 5/20/2022 | Conditional Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 6/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 6/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 6/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 6/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 6/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 7/5/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 7/5/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 7/5/2022 | Approved | VINCENT HANLEY |
| Insulation | 7/14/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/22/2022 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 7/29/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/29/2022 | Approved | VINCENT HANLEY |
| Shower Pan | 8/29/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 9/2/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 5/8/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/8/2023 | Approved | VINCENT HANLEY |
| Final | 5/8/2023 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/8/2023 | Approved | VINCENT HANLEY |
| Green Building Final | 5/8/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 5/8/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/8/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/8/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 5/8/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Smoke Detectors | 5/8/2023 | Approved | VINCENT HANLEY |