10353-10355 N INDEPENDENCE AVE 91311
Certificate Information: 10353-10355 N INDEPENDENCE AVE 91311
- Application / Permit
- 21014-20000-02146
- Plan Check / Job No.
- B21VN05227
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 19' X 23'-9" REC ROOM W/ HALF BATHROOM ADDITION TO (E) SINGLE FAMILY DWELLING W/ ATTACHED ACCESSORY DWELLING UNIT. ALL WORK PER WFPP
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- CofO Issued on 9/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2021 | SERGIO MUNIZ |
| Corrections Issued | 4/30/2021 | SERGIO MUNIZ |
| Plan Check Approved | 9/15/2021 | JEROME MAGAT PALMA |
| Issued | 9/15/2021 | APPLICANT |
| Building Plans Picked Up | 9/17/2021 | APPLICANT |
| CofO in Progress | 1/18/2022 | VINCENT HANLEY |
| CofO Issued | 9/10/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/10/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 8/18/2021 | GABRIEL ROBLES |
| Tract Map conditions | Cleared | 8/18/2021 | MIGUEL GAMBOA |
| Grading Pre-Inspection | Cleared | 8/24/2021 | TIMOTHY POWELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/7/2021 | Approved | JEFFREY PARD |
| Underground Mechanical | 10/7/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 10/18/2021 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 11/19/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 11/19/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 11/19/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 11/19/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 11/29/2021 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 1/14/2022 | Approved | VINCENT HANLEY |
| Final | 1/14/2022 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 1/14/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 1/14/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/14/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/14/2022 | SGSOV Approved | VINCENT HANLEY |