20604-20606 W LEMAY ST 91306

Certificate Information: 20604-20606 W LEMAY ST 91306

Application / Permit
21014-20000-02133
Plan Check / Job No.
B21VN05206
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) IRRGULAR 17'-6" X 31'-10" ADDITION TO (E) 18-6" X 21'-10" GARAGE AND CONVERT GARAGE AND ADDITION TO (N) ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) ALL WORK PER WFPP
Permit Issued
Issued on 10/25/2021
Issuing Office
Current Status
CofO Issued on 11/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/16/2021 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 6/21/2021 OMID HEDAYAT
Building Plans Picked Up 6/21/2021 APPLICANT
Plan Check Approved 10/25/2021 SEWADA ZADOORAN MILAGARDI
Issued 10/25/2021 APPLICANT
CofO in Progress 11/18/2022 STEVEN BACK
Permit Finaled 11/23/2022 JOHN JANSON
CofO Issued 11/23/2022 JOHN JANSON
Permit Finaled 11/23/2022 JOHN JANSON

Permit Application Clearance Information

Miscellaneous Cleared 7/8/2021 LAUREN PADICK
Address approval Cleared 9/27/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/27/2021 CARLOS AGUILERA
Low Impact Development Cleared 9/27/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 9/27/2021 CARLOS AGUILERA
Sewer availability Cleared 9/27/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/7/2022 Conditional Approval STEVEN BACK
Final 1/10/2022 Corrections Issued STEVEN BACK
PLUMBING-Rough 1/10/2022 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 1/13/2022 Approved STEVEN BACK
Footing/Foundation/Slab 1/13/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Partial Approval STEVEN BACK
ELECTRICAL-Rough 3/29/2022 Not Ready for Inspection STEVEN BACK
HVAC-Rough 3/29/2022 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 3/29/2022 Partial Approval STEVEN BACK
PLUMBING-Rough 3/29/2022 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 5/4/2022 Partial Approval STEVEN BACK
ELECTRICAL-Rough 5/4/2022 Approved STEVEN BACK
Final 5/4/2022 Corrections Issued STEVEN BACK
Green Building Rough 5/4/2022 Approved STEVEN BACK
HVAC-Rough 5/4/2022 Approved STEVEN BACK
PLUMBING-Rough 5/4/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 6/9/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Approved STEVEN BACK
Insulation 6/9/2022 Approved STEVEN BACK
Service/Power Release 6/9/2022 Not Ready for Inspection STEVEN BACK
Drywall Nailing 6/16/2022 Approved STEVEN BACK
Interior/Exterior Lathing 6/16/2022 Approved STEVEN BACK
Final 9/7/2022 Corrections Issued STEVEN BACK
Green Building Final 9/7/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved STEVEN BACK
Smoke Detectors 9/7/2022 Approved STEVEN BACK
ELECTRICAL-Final 11/18/2022 Approved STEVEN BACK
Final 11/18/2022 OK to Issue CofO STEVEN BACK
HVAC-Final 11/18/2022 Approved STEVEN BACK
PLUMBING-Final 11/18/2022 Approved STEVEN BACK
Special/Order Compliance 11/18/2022 Partial Inspection MORRIS JACKSON