22041 W RUNNYMEDE ST 91303

Certificate Information: 22041 W RUNNYMEDE ST 91303

Application / Permit
21014-20000-02118
Plan Check / Job No.
B21VN05166
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRREGULAR SHAPED 26'-10" x 23'-5" TO (E) S.F.D. PER ENGINEERING
Permit Issued
Issued on 8/16/2021
Issuing Office
Current Status
CofO Issued on 2/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2021 APPLICANT
Assigned to Plan Check Engineer 5/5/2021 ALFRED RAMIREZ
Corrections Issued 5/5/2021 ALFRED RAMIREZ
Applicant returned to address corrections 8/5/2021 ALFRED RAMIREZ
Issued 8/16/2021 APPLICANT
Building Plans Picked Up 8/16/2021 APPLICANT
CofO in Progress 2/10/2022 JOHN JANSON
Permit Finaled 2/10/2022 JOHN JANSON
CofO Issued 2/10/2022 JOHN JANSON
Permit Finaled 2/10/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/10/2021 LEE GUILBEAUX
Sewer availability Cleared 5/10/2021 LEE GUILBEAUX
Low Impact Development Cleared 7/28/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/10/2021 CARLOS AGUILERA

Contact Information

Contractor Cabrera Roofing Construction Inc; Lic. No.: 1030287-B 7441 RIVERTON AVENUE      SUN VALLEY, CA 91352
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/18/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 8/18/2021 Corrections Issued DAVID STEPANYAN
Special/Order Compliance 8/18/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 8/24/2021 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 9/3/2021 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 9/9/2021 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Partial Approval DAVID STEPANYAN
ELECTRICAL-Rough 10/14/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Partial Approval TROY SANDERS
HVAC-Rough 10/14/2021 Approved TROY SANDERS
PLUMBING-Rough 10/14/2021 Approved TROY SANDERS
Service/Power Release 10/14/2021 Approved TROY SANDERS
Interior/Exterior Lathing 10/18/2021 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 10/22/2021 Approved DAVID STEPANYAN
Green Building Rough 10/22/2021 Approved DAVID STEPANYAN
Insulation 10/22/2021 Not Ready for Inspection DAVID STEPANYAN
Interior/Exterior Lathing 10/22/2021 Partial Approval DAVID STEPANYAN
Insulation 10/25/2021 Approved JESUS PINEDA
Drywall Nailing 11/3/2021 Approved JESUS PINEDA
Interior/Exterior Lathing 11/18/2021 Approved DAVID STEPANYAN
Shower Pan 11/18/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 11/22/2021 Corrections Issued DAVID STEPANYAN
Final 11/22/2021 Corrections Issued DAVID STEPANYAN
Green Building Final 11/22/2021 Corrections Issued DAVID STEPANYAN
HVAC-Final 11/22/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 11/22/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/22/2021 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 11/22/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Final 12/14/2021 Approved DAVID STEPANYAN
Final 12/14/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 12/14/2021 Not Ready for Inspection DAVID STEPANYAN
HVAC-Final 12/14/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Final 12/14/2021 Approved DAVID STEPANYAN
Smoke Detectors 12/14/2021 Approved DAVID STEPANYAN
Final 2/1/2022 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 2/1/2022 Approved DAVID SCANTLIN
Final 2/10/2022 OK to Issue CofO DAVID SCANTLIN