12631 W MARTHA ST 91607
Certificate Information: 12631 W MARTHA ST 91607
- Application / Permit
- 21014-20000-02108
- Plan Check / Job No.
- B21VN05129
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 541.6 SQ. FT. ADDITION OF A MASTER BEDROOM, BATHROOM AND LAUNDRY, WITH AN INTERIOR REMODEL.
- Permit Issued
- Issued on 8/23/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2021 | JESSE ARELLANO |
| Corrections Issued | 5/1/2021 | JESSE ARELLANO |
| Plan Check Approved | 1/21/2022 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| Issued | 8/23/2023 | APPLICANT |
| CofO in Progress | 5/2/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 5/8/2025 | RUBEN SALAS |
| CofO Issued | 5/8/2025 | RUBEN SALAS |
| Permit Finaled | 5/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/14/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 12/10/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2021 | LEE GUILBEAUX |
| Green Code | Cleared | 1/21/2022 | JESSE ARELLANO |
Contact Information
| Contractor | Yay Construction Inc; Lic. No.: 1078903-B | 5755 WILKINSON AVE VALLEY VILLAGE, CA 91607 |
| Engineer | Schwartzberg,, Leo Joshua; Lic. No.: C51851 | 7547 SEDGEWICK CT WEST HILLS, CA 91304 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/28/2023 | Approved | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 9/15/2023 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 9/18/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 9/26/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/12/2023 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 10/12/2023 | Not Ready for Inspection | KIRK SANDERS |
| Underground Mechanical | 10/12/2023 | Approved | KIRK SANDERS |
| Deputy Drilled-In Anchors | 10/13/2023 | Conditional Approval | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 10/17/2023 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Partial Approval | JUAN VALENZUELA |
| Insulation | 10/17/2023 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/30/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 10/30/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Wood Frame | 10/30/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Corrections Issued | KIRK SANDERS |
| Shower Pan | 11/3/2023 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | WILLIAM WREN |
| Interior/Exterior Lathing | 11/13/2023 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 11/20/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 11/20/2023 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 11/20/2023 | Partial Approval | RAUL OLAGI |
| Wood Frame | 11/20/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/28/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 11/28/2023 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 11/28/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 11/28/2023 | Partial Approval | KIRK SANDERS |
| Wood Frame | 11/28/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 12/4/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 12/4/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 12/7/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 12/7/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 12/13/2023 | Approved | JOSE AVILA |
| Insulation | 12/18/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 12/22/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 12/22/2023 | Approved | KIRK SANDERS |
| Shower Pan | 12/22/2023 | Approved | KIRK SANDERS |
| Final | 8/26/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 8/26/2024 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 8/26/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 8/26/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 5/2/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Green Building Final | 5/2/2025 | Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 5/2/2025 | Approved | GAREN HAYRAPETYAN |