18148 W LULL ST 91335

Certificate Information: 18148 W LULL ST 91335

Application / Permit
21014-20000-02106
Plan Check / Job No.
B21VN05128
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) SFD EXCEPT FOR (7'-10") LINEAR FEET OF WALL AT REAR, AND BUILD NEW 2 STORY (30'-0"x 41'-0") SFD W/ NEW NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/25/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 PETER MOSESIAN
Corrections Issued 6/9/2021 PETER MOSESIAN
Quality Review Completed 6/21/2021 OMID HEDAYAT
Building Plans Picked Up 6/25/2021 APPLICANT
Plan Check Approved 10/4/2021 PETER MOSESIAN
Issued 10/25/2022 APPLICANT
CofO in Progress 7/25/2024 JEFFREY BULL
Permit Finaled 9/27/2024 JOHN JANSON
CofO Issued 9/27/2024 JOHN JANSON
Permit Finaled 9/27/2024 JOHN JANSON

Permit Application Clearance Information

Sewer availability Cleared 6/28/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/2/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 9/23/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/24/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/25/2023 Approved JEFFREY BULL
Deputy Drilled-In Anchors 7/7/2023 Conditional Approval JEFFREY BULL
Footing/Foundation/Slab 7/12/2023 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 7/27/2023 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 7/31/2023 Corrections Issued JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Partial Approval JEFFREY BULL
Deputy Wood Construction 9/27/2023 Conditional Approval JEFFREY BULL
Deputy Wood Construction 10/12/2023 Conditional Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Approved JEFFREY BULL
Green Building Rough 10/16/2023 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 11/1/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 11/1/2023 Approved JEFFREY BULL
Green Building Rough 11/1/2023 Approved JEFFREY BULL
HVAC-Rough 11/1/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 11/1/2023 Partial Approval JEFFREY BULL
PLUMBING-Rough 11/1/2023 Approved JEFFREY BULL
Sewer 11/1/2023 Approved JEFFREY BULL
Drywall Nailing 11/15/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 3/27/2024 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 4/2/2024 Approved JEFFREY BULL
Final 6/13/2024 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 6/13/2024 Approved JEFFREY BULL
Green Building Final 6/13/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 6/13/2024 Approved JEFFREY BULL
Final 7/25/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 7/25/2024 Approved JEFFREY BULL