7840 N BABCOCK AVE 91605
Certificate Information: 7840 N BABCOCK AVE 91605
- Application / Permit
- 21014-20000-02103
- Plan Check / Job No.
- B21VN05121
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/15/2021
- Issuing Office
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | COLIN LOREDO |
| Corrections Issued | 6/10/2021 | COLIN LOREDO |
| Quality Review Completed | 6/21/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/29/2021 | APPLICANT |
| Applicant returned to address corrections | 9/16/2021 | COLIN LOREDO |
| Plan Check Approved | 10/7/2021 | COLIN LOREDO |
| Issued | 10/15/2021 | APPLICANT |
| CofO in Progress | 1/6/2023 | MATTHEW NELSON |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
| CofO Issued | 1/14/2023 | MICHAEL SMITH |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/15/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/20/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 9/29/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Ind Construction Llc; Lic. No.: 937833-B | 16430 VENTURA BLVD STE 208 ENCINO, CA 91436 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/9/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 5/9/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 5/10/2022 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 6/17/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Wood Frame | 6/17/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Approved | MATTHEW NELSON |
| Insulation | 6/30/2022 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2022 | Partial Approval | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 9/8/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 9/12/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 9/15/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/15/2022 | Approved | WILLIAM WREN |
| MERV13>=Rough | 9/15/2022 | Approved | WILLIAM WREN |
| Shower Pan | 9/15/2022 | Approved | WILLIAM WREN |
| Insulation | 9/21/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 9/21/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 10/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 10/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 10/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 12/28/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/28/2022 | Approved | MATTHEW NELSON |
| Green Building Final | 12/28/2022 | Approved | MATTHEW NELSON |
| MERV13>=Final | 12/28/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 12/28/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 1/5/2023 | Approved | MATTHEW NELSON |
| Final | 1/5/2023 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 1/5/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 1/5/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/5/2023 | SGSOV Approved | MATTHEW NELSON |