17949 W VANOWEN ST 91335

Certificate Information: 17949 W VANOWEN ST 91335

Application / Permit
21014-20000-02046
Plan Check / Job No.
B21VN04959
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTERIOR ALTERATIONS, TO CONSIST OF A MAJOR REMODEL, AND ADDITION OF A 21'6" x 22' TO THE (E) SINGLE-FAMILY DWELLING. NFPA-13D REQUIRED THROUGHOUT.
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 5/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2021 APPLICANT
Assigned to Plan Check Engineer 4/28/2021 LUIS RINCON
Corrections Issued 4/28/2021 LUIS RINCON
Applicant returned to address corrections 7/4/2021 LUIS RINCON
Applicant returned to address corrections 7/7/2021 LUIS RINCON
Plan Check Approved 8/3/2021 LUIS RINCON
Building Plans Picked Up 8/9/2021 APPLICANT
Issued 8/18/2021 APPLICANT
CofO in Progress 4/5/2023 JEFFREY BULL
CofO Issued 5/2/2023 MICHAEL SMITH
Permit Finaled 5/2/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/30/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/30/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 5/10/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/3/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 3/3/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/15/2022 Partial Approval VINCENT HANLEY
Green Building Rough 3/15/2022 Not Ready for Inspection VINCENT HANLEY
Insulation 3/15/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/31/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 5/31/2022 Approved STEVEN BACK
Green Building Rough 5/31/2022 Not Ready for Inspection STEVEN BACK
HVAC-Rough 5/31/2022 Corrections Issued STEVEN BACK
PLUMBING-Rough 5/31/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 6/24/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 6/24/2022 Partial Approval VINCENT HANLEY
Green Building Rough 6/24/2022 Approved VINCENT HANLEY
HVAC-Rough 6/24/2022 Approved VINCENT HANLEY
PLUMBING-Rough 6/24/2022 Approved VINCENT HANLEY
Wood Frame 6/24/2022 Approved VINCENT HANLEY
Drywall Nailing 9/20/2022 Conditional Approval KRISTEN CAUSEY
Interior/Exterior Lathing 9/30/2022 Approved MORRIS JACKSON
Shower Pan 9/30/2022 Approved MORRIS JACKSON
Shower Pan 1/30/2023 Not Ready for Inspection VINCENT HANLEY
Drywall Nailing 3/21/2023 Approved JEFFREY PARD
Final 3/21/2023 Corrections Issued JEFFREY PARD
Green Building Final 3/21/2023 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Approved JEFFREY PARD
Smoke Detectors 3/21/2023 Approved JEFFREY PARD
ELECTRICAL-Final 4/4/2023 Approved JEFFREY BULL
Final 4/4/2023 OK to Issue CofO JEFFREY BULL
HVAC-Final 4/4/2023 Approved JEFFREY BULL
PLUMBING-Final 4/4/2023 Approved JEFFREY BULL
Special/Order Compliance 4/4/2023 Partial Inspection MORRIS JACKSON