18826 W ARMINTA ST 91335
Certificate Information: 18826 W ARMINTA ST 91335
- Application / Permit
- 21014-20000-02007
- Plan Check / Job No.
- B21VN04866
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED RECREATION ROOM BUILDING TO ACCESSORY DWELLING UNIT AND ADDITION
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 5/2/2021 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 5/4/2021 | APPLICANT |
| Applicant returned to address corrections | 5/18/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 6/3/2022 | FERNANDO FLORES |
| Issued | 6/3/2022 | APPLICANT |
| CofO in Progress | 10/20/2023 | JEFFREY BULL |
| Permit Finaled | 11/16/2023 | JOHN JANSON |
| CofO Issued | 11/16/2023 | JOHN JANSON |
| Permit Finaled | 11/16/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/22/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 3/16/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 4/1/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 5/18/2022 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/5/2022 | Partial Approval | DAVID SANDOVAL |
| Underground Mechanical | 10/5/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 10/28/2022 | Conditional Approval | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 10/28/2022 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 10/28/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 2/13/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 2/13/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 2/14/2023 | Conditional Approval | JEFFREY BULL |
| Gas Test | 2/15/2023 | Approved | JEFFREY BULL |
| Rough-Elec/Plmb/HVAC | 2/15/2023 | Approved | JEFFREY BULL |
| Underground Mechanical | 2/15/2023 | Approved | JEFFREY BULL |
| Insulation | 3/24/2023 | Conditional Approval | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 3/24/2023 | Approved | KRISTEN CAUSEY |
| Shower Pan | 3/24/2023 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 4/6/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 4/6/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 8/21/2023 | Approved | JEFFREY BULL |
| Final | 8/21/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 8/21/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 8/21/2023 | Approved | JEFFREY BULL |
| Final | 10/20/2023 | OK to Issue CofO | JEFFREY BULL |
| Service/Power Release | 11/15/2023 | Approved | JEFFREY BULL |