11008 N HASKELL AVE 91344
Certificate Information: 11008 N HASKELL AVE 91344
- Application / Permit
- 21014-20000-01995
- Plan Check / Job No.
- B21VN04844
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 5' X 17'-6" ADDITION TO ENLARGE GARAGE. 35' X 39'-6" IRREG SHAPED ACCESSORY DWELLING UNIT ADDITION (1200 SQ FT) TO (E) DETACHED GARAGE PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 5/21/2022
- Issuing Office
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 5/20/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 5/5/2022 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 5/17/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 5/19/2022 | JEROME MAGAT PALMA |
| Issued | 5/21/2022 | APPLICANT |
| Building Plans Picked Up | 5/24/2022 | APPLICANT |
| CofO in Progress | 7/1/2024 | JAVIER RAMOS JR |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
| CofO Issued | 8/7/2024 | RUBEN SALAS |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/7/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 12/10/2021 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 4/25/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 5/18/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/16/2022 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/16/2022 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/29/2022 | Approved | JAVIER RAMOS JR |
| Wood Frame | 11/23/2022 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/12/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/12/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 1/12/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 1/12/2023 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 1/12/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/12/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 1/12/2023 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 1/12/2023 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 1/20/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 1/20/2023 | Partial Approval | WILLIAM WREN |
| Shower Pan | 1/20/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 1/31/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 1/31/2023 | Approved | JOHN COLEMAN |
| Sewer | 2/13/2023 | Approved | JAVIER RAMOS JR |
| Gas Test | 3/20/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 3/20/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/27/2023 | Approved | JAVIER RAMOS JR |
| Final | 4/27/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 4/27/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 4/27/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/27/2023 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 4/27/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/27/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/27/2023 | Approved | JAVIER RAMOS JR |
| Final | 6/28/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 6/28/2024 | Approved | JAVIER RAMOS JR |