11212 W HORTENSE ST 91602
Certificate Information: 11212 W HORTENSE ST 91602
- Application / Permit
- 21014-20000-01965
- Plan Check / Job No.
- B21VN04771
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 33'-5" X 47'-4" IRREGULAR SHAPED ADDITION TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER DESIGN.
- Permit Issued
- Issued on 3/29/2022
- Issuing Office
- Current Status
- Issued on 3/29/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2021 | RAPHAEL ROSAS |
| Corrections Issued | 5/1/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 11/23/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 12/7/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 12/8/2021 | APPLICANT |
| Issued | 3/29/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/17/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 11/9/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 11/15/2021 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Rodriguez Construction Group Inc; Lic. No.: 1087350-B | 320 W 49TH ST LOS ANGELES, CA 90037 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/28/2022 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/29/2022 | Corrections Issued | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 6/3/2022 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 6/6/2022 | Conditional Approval | MICHAEL SMITH |
| Excavation/Setback/Form/Re-Bar | 6/8/2022 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/9/2022 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 6/24/2022 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/29/2022 | Partial Approval | MATT KELLERMAN |
| Rough-Elec/Plmb/HVAC | 8/1/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 8/1/2022 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/9/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 8/9/2022 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 8/9/2022 | Approved | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 8/9/2022 | Approved | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 8/12/2022 | Conditional Approval | CALEB MEISTER |
| Insulation | 8/16/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 8/16/2022 | Partial Approval | CALEB MEISTER |
| Drywall Nailing | 8/25/2022 | Approved | THOMAS FINNILA |
| Shower Pan | 8/25/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/29/2022 | Approved | CALEB MEISTER |
| Underground Mechanical | 9/19/2022 | Approved | CALEB MEISTER |
| Service/Power Release | 10/26/2022 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 11/7/2022 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 11/14/2022 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 12/5/2022 | Approved | JACK KARGODORIAN |