11260 W BLIX ST 91602

Certificate Information: 11260 W BLIX ST 91602

Application / Permit
21014-20000-01956
Plan Check / Job No.
B21VN04738
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
34' X 14'10 " (IRR .SHAPE) ADDITION TO ENLARGE THE MASTER BEDROOM AND BATHROOM, ENLARGE THE LIVING ROOM AND INTERIOR REMODEL. ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 5/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2021 APPLICANT
Assigned to Plan Check Engineer 4/23/2021 JEFFREY TANGONAN
Corrections Issued 4/24/2021 JEFFREY TANGONAN
Plan Check Approved 6/10/2021 JEFFREY TANGONAN
Building Plans Picked Up 7/13/2021 APPLICANT
Issued 8/18/2021 APPLICANT
CofO in Progress 4/28/2022 DAVID MATSON
Permit Finaled 5/12/2022 MICHAEL SMITH
CofO Issued 5/12/2022 MICHAEL SMITH
Permit Finaled 5/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/26/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/3/2021 CARLOS AGUILERA
Sewer availability Cleared 6/3/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Valencia,, Byron Steve; Lic. No.: C87372 16200 VENTURA BLVD STE 317      ENCINO, CA 91436

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/8/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 10/8/2021 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 10/14/2021 Corrections Issued ASHLEY THOMPSON
Deputy Drilled-In Anchors 10/14/2021 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 10/14/2021 Approved ASHLEY THOMPSON
Footing/Foundation/Slab 10/14/2021 Approved ASHLEY THOMPSON
Special/Order Compliance 10/14/2021 Partial Inspection MICHAEL PELHAM
PLUMBING-Rough 11/1/2021 Partial Inspection THOMAS FINNILA
PLUMBING-Rough 11/3/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 11/5/2021 Partial Approval THOMAS FINNILA
Wood Frame 11/5/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 12/8/2021 Corrections Issued MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Not Ready for Inspection MATT KELLERMAN
Green Building Rough 12/8/2021 Not Ready for Inspection MATT KELLERMAN
MERV13>=Rough 12/8/2021 Not Ready for Inspection MATT KELLERMAN
Rough-Elec/Plmb/HVAC 12/8/2021 Not Ready for Inspection MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Approval THOMAS FINNILA
Rough-Elec/Plmb/HVAC 12/13/2021 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/21/2021 Corrections Issued THOMAS FINNILA
Rough-Elec/Plmb/HVAC 12/21/2021 No Access for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 12/23/2021 Partial Approval THOMAS FINNILA
MERV13>=Rough 12/23/2021 Approved THOMAS FINNILA
Rough-Elec/Plmb/HVAC 12/23/2021 Partial Approval THOMAS FINNILA
Rough-Elec/Plmb/HVAC 1/5/2022 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 1/10/2022 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 1/18/2022 Corrections Issued MICHAEL TEMPLE
Green Building Rough 1/18/2022 Not Ready for Inspection MICHAEL TEMPLE
Interior/Exterior Lathing 1/18/2022 Not Ready for Inspection MICHAEL TEMPLE
Rough-Elec/Plmb/HVAC 1/18/2022 Corrections Issued MICHAEL TEMPLE
Interior/Exterior Lathing 1/21/2022 Partial Approval MATT KELLERMAN
Rough-Elec/Plmb/HVAC 1/21/2022 Not Ready for Inspection MATT KELLERMAN
BUILDING-Rough-Frame 1/26/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 1/26/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 1/26/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Rough-Elec/Plmb/HVAC 1/26/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 1/28/2022 Not Ready for Inspection RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 1/28/2022 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 2/1/2022 Partial Approval THOMAS FINNILA
Green Building Rough 2/1/2022 Not Ready for Inspection THOMAS FINNILA
Rough-Elec/Plmb/HVAC 2/1/2022 Partial Approval THOMAS FINNILA
Insulation 2/4/2022 Approved THOMAS FINNILA
Drywall Nailing 2/9/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 4/1/2022 Approved THOMAS FINNILA
Green Building Final 4/1/2022 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 4/1/2022 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 4/1/2022 SGSOV Not Ready THOMAS FINNILA
Final 4/6/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 4/18/2022 Corrections Issued THOMAS FINNILA
Final 4/18/2022 Not Ready for Inspection THOMAS FINNILA
Green Building Final 4/18/2022 Approved THOMAS FINNILA
HVAC-Final 4/18/2022 Approved THOMAS FINNILA
MERV13>=Final 4/18/2022 Approved THOMAS FINNILA
PLUMBING-Final 4/18/2022 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 4/18/2022 SGSOV Approved THOMAS FINNILA
Smoke Detectors 4/18/2022 Approved THOMAS FINNILA
ELECTRICAL-Final 4/26/2022 Corrections Issued DAVID MATSON
Final 4/27/2022 OK to Issue CofO DAVID MATSON
Service/Power Release 4/27/2022 Approved DAVID MATSON