5900 N WISH AVE 91316

Certificate Information: 5900 N WISH AVE 91316

Application / Permit
21014-20000-01949
Plan Check / Job No.
B21VN04709
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
17'-7" X 10'-4" ADDITION OF A SUN ROOM AND (N) 17'-7" X 10'-4" ATTACHED PATIO COVER TO (E) SINGLE FAMLIY DWELLING.
Permit Issued
Issued on 3/24/2022
Issuing Office
Current Status
CofO Issued on 8/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2021 APPLICANT
Assigned to Plan Check Engineer 4/21/2021 SERGIO MUNIZ
Corrections Issued 4/21/2021 SERGIO MUNIZ
Applicant returned to address corrections 4/30/2021 SERGIO MUNIZ
Building Plans Picked Up 5/3/2021 APPLICANT
Plan Check Approved 3/15/2022 SERGIO MUNIZ
Issued 3/24/2022 APPLICANT
CofO in Progress 7/28/2025 MORRIS JACKSON
Permit Finaled 8/5/2025 DANIEL ORRANTE
CofO Issued 8/5/2025 DANIEL ORRANTE
Permit Finaled 8/5/2025 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/6/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 5/6/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/10/2024 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 12/18/2024 Approved JOHN COLEMAN
Footing/Foundation/Slab 12/18/2024 Approved JOHN COLEMAN
PLUMBING-Rough 12/18/2024 Approved JOHN COLEMAN
Underground Mechanical 12/18/2024 Approved JOHN COLEMAN
BUILDING-Rough-Frame 1/24/2025 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 1/24/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Partial Approval MORRIS JACKSON
Green Building Rough 1/24/2025 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 2/3/2025 Partial Approval JON MCHUGH
Green Building Rough 2/3/2025 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 2/6/2025 Partial Approval MORRIS JACKSON
Final 2/6/2025 Not Ready for Inspection MORRIS JACKSON
Green Building Final 2/6/2025 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 2/6/2025 Partial Approval MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Not Ready MORRIS JACKSON
Smoke Detectors 2/6/2025 Not Ready for Inspection MORRIS JACKSON
Insulation 2/12/2025 Approved MORRIS JACKSON
Drywall Nailing 2/28/2025 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Not Ready for Inspection JON MCHUGH
HVAC-Rough 2/28/2025 Corrections Issued JON MCHUGH
Drywall Nailing 3/12/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Approved MORRIS JACKSON
HVAC-Rough 3/12/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/17/2025 Partial Approval GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 6/2/2025 Approved MORRIS JACKSON
BUILDING-Rough-Frame 6/27/2025 Approved MORRIS JACKSON
Final 6/27/2025 Corrections Issued MORRIS JACKSON
Green Building Final 6/27/2025 Approved MORRIS JACKSON
Green Building Rough 6/27/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Approved MORRIS JACKSON
Smoke Detectors 6/27/2025 Approved MORRIS JACKSON
Final 7/10/2025 OK to Issue CofO MORRIS JACKSON