4906 N GLEN IRIS AVE 90041

Certificate Information: 4906 N GLEN IRIS AVE 90041

Application / Permit
21014-20000-01948
Plan Check / Job No.
B21VN04704
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
13'3" x 31' ADDITION AND CONVERT THE (E) 13'3" x 13'6" STORAGE ROOM INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g). ALL WORK PER WFPP
Permit Issued
Issued on 8/31/2021
Issuing Office
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 4/26/2021 JEFFREY TANGONAN
Corrections Issued 4/26/2021 JEFFREY TANGONAN
Applicant returned to address corrections 8/26/2021 JEFFREY TANGONAN
Issued 8/31/2021 APPLICANT
Building Plans Picked Up 9/2/2021 APPLICANT
CofO in Progress 7/27/2022 CRAIG VAUGHAN
Permit Finaled 8/2/2022 DEROLD HAUFF
CofO Issued 8/2/2022 DEROLD HAUFF
Permit Finaled 8/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 5/18/2021 MICHAEL SOTO
Construction near power lines Cleared 7/7/2021 RIDWAN HARDY
Address approval Cleared 7/31/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 7/31/2021 THOMAS LANG
Grading Pre-Inspection Cleared 8/4/2021 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 8/18/2021 THOMAS LANG
Sewer availability Cleared 8/18/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/2/2021 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/10/2021 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 1/20/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 2/4/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 2/15/2022 Partial Approval COREY HUPP
Interior/Exterior Lathing 2/15/2022 Partial Approval COREY HUPP
PLUMBING-Rough 2/15/2022 Approved COREY HUPP
BUILDING-Rough-Frame 2/22/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 2/22/2022 Approved CRAIG VAUGHAN
Green Building Rough 2/22/2022 Approved CRAIG VAUGHAN
HVAC-Rough 2/22/2022 Approved CRAIG VAUGHAN
Insulation 2/25/2022 Approved CHARLES BOGHOSKHAN
Drywall Nailing 2/28/2022 Approved CHARLES BOGHOSKHAN
Final 5/27/2022 Corrections Issued CRAIG VAUGHAN
Green Building Final 5/27/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/27/2022 SGSOV Not Required CRAIG VAUGHAN
Smoke Detectors 5/27/2022 Approved CRAIG VAUGHAN
Final 7/20/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 7/26/2022 Approved CRAIG VAUGHAN
Final 7/26/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 7/26/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 7/26/2022 Approved CRAIG VAUGHAN