5718 N BURNET AVE 91411

Certificate Information: 5718 N BURNET AVE 91411

Application / Permit
21014-20000-01934
Plan Check / Job No.
B21VN04673
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
26'-0" X 44'-11" IRREGULAR SHAPED ADDITION AND INTERIOR REMODEL TO (E) SFD, REMODEL (E) KITCHEN, RELOCATING THE (E) LAUNDRY ROOM, CONVERT THE (E) BATHROOM INTO A (N) MASTER BATHROOM, RELOCATE THE (E) BEDROOM TO CREATE A NEW MASTER BEDROOM AND NEW DEN.
Permit Issued
Issued on 11/1/2021
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 ARTIN ZARUKIAN
Corrections Issued 5/1/2021 ARTIN ZARUKIAN
Plan Check Approved 11/1/2021 ARTIN ZARUKIAN
Issued 11/1/2021 APPLICANT
Building Plans Picked Up 11/2/2021 APPLICANT
CofO in Progress 12/10/2022 RYAN SALAZAR
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/25/2021 CARLOS AGUILERA
Sewer availability Cleared 5/25/2021 CARLOS AGUILERA
Low Impact Development Cleared 10/12/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 10/15/2021 CARLOS AGUILERA

Contact Information

Contractor Pearl Remodeling; Lic. No.: 955824-B 6803 YARMOUTH AVENUE      RESEDA, CA 91335
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/13/2022 No Access for Inspection RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 1/18/2022 Approved RICHARD DOCKUS
Footing/Foundation/Slab 1/18/2022 Approved RICHARD DOCKUS
Deputy Reinf. Concrete 1/19/2022 No Access for Inspection RICHARD DOCKUS
Deputy Drilled-In Anchors 2/15/2022 No Access for Inspection RICHARD DOCKUS
Drywall Nailing 2/15/2022 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 2/15/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/15/2022 Corrections Issued RAUL OLAGI
Green Building Rough 2/15/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 2/15/2022 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 2/17/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 2/17/2022 Approved RICHARD DOCKUS
Deputy Wood Construction 2/18/2022 Conditional Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 4/1/2022 Corrections Issued RICHARD DOCKUS
Green Building Rough 4/1/2022 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 4/11/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 4/11/2022 Approved RICHARD DOCKUS
HVAC-Rough 4/11/2022 Corrections Issued RICHARD DOCKUS
Insulation 4/11/2022 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 4/11/2022 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 4/14/2022 Partial Approval RICHARD DOCKUS
Deputy Wood Construction 4/14/2022 Approved RICHARD DOCKUS
HVAC-Rough 4/14/2022 Corrections Issued RICHARD DOCKUS
Insulation 4/14/2022 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 4/19/2022 Approved JOHN HAYES
HVAC-Rough 4/19/2022 Approved JOHN HAYES
Insulation 4/19/2022 Approved JOHN HAYES
Interior/Exterior Lathing 4/19/2022 Partial Approval JOHN HAYES
Drywall Nailing 4/29/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 5/12/2022 Approved RICHARD DOCKUS
Final 8/30/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 8/30/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 8/30/2022 Corrections Issued RICHARD DOCKUS
Final 9/6/2022 No Access for Inspection RICHARD DOCKUS
Smoke Detectors 9/6/2022 No Access for Inspection RICHARD DOCKUS
Final 12/2/2022 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 12/2/2022 Approved RYAN SALAZAR
ELECTRICAL-Final 12/9/2022 Approved RYAN SALAZAR
Final 12/9/2022 OK to Issue CofO RYAN SALAZAR
HVAC-Final 12/9/2022 Approved RYAN SALAZAR
PLUMBING-Final 12/9/2022 Approved RYAN SALAZAR