8005 N LOUISE AVE 91325

Certificate Information: 8005 N LOUISE AVE 91325

Application / Permit
21014-20000-01917
Plan Check / Job No.
B21VN04628
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 13'-10" X 19'-10" DETACHED GARAGE AND ADD 23'-8" X 40' IRREGULAR SHAPE TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/19/2021
Issuing Office
Current Status
CofO Issued on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2021 APPLICANT
Assigned to Plan Check Engineer 5/10/2021 RAPHAEL ROSAS
Corrections Issued 5/10/2021 RAPHAEL ROSAS
Plan Check Approved 9/21/2021 RAPHAEL ROSAS
Building Plans Picked Up 9/23/2021 APPLICANT
Issued 10/19/2021 APPLICANT
CofO in Progress 1/16/2025 RAUL OLAGI
Permit Finaled 1/17/2025 RUBEN SALAS
CofO Issued 1/17/2025 RUBEN SALAS
Permit Finaled 1/17/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/24/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/1/2021 CARLOS AGUILERA
Sewer availability Cleared 6/1/2021 CARLOS AGUILERA
Low Impact Development Cleared 9/10/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/10/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/3/2023 Approved RAUL OLAGI
Excavation/Setback/Form/Re-Bar 1/18/2024 Partial Inspection RAUL OLAGI
PLUMBING-Rough 1/18/2024 Partial Approval RAUL OLAGI
Sewer 1/18/2024 Approved RAUL OLAGI
Footing/Foundation/Slab 1/31/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/26/2024 Partial Approval CRAIG DAVIS
Interior/Exterior Lathing 3/11/2024 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 4/12/2024 Approved RAUL OLAGI
Green Building Rough 4/12/2024 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 4/12/2024 Approved RAUL OLAGI
Insulation 4/19/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Approved RAUL OLAGI
Drywall Nailing 4/29/2024 Approved RAUL OLAGI
Shower Pan 4/29/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 5/6/2024 Approved RAUL OLAGI
Underground Mechanical 7/19/2024 Approved RAUL OLAGI
ELECTRICAL-Final 9/3/2024 Approved RAUL OLAGI
Final 9/3/2024 Corrections Issued RAUL OLAGI
Green Building Final 9/3/2024 Approved RAUL OLAGI
HVAC-Final 9/3/2024 Approved RAUL OLAGI
PLUMBING-Final 9/3/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 9/3/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 9/3/2024 Approved RAUL OLAGI
Final 1/16/2025 OK to Issue CofO RAUL OLAGI