13630 W HARTLAND ST 91405

Certificate Information: 13630 W HARTLAND ST 91405

Application / Permit
21014-20000-01916
Plan Check / Job No.
B21VN04625
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20'-1" X 44'-3" IRREG SHAPED ADDITION AND REMODEL TO SINGLE FAMILY DWELLING TO ENLARGE (E) BEDROOM AND LIVING ROOM, AND TO ADD NEW BEDROOM AND BATHROOM.
Permit Issued
Issued on 9/28/2021
Issuing Office
Current Status
CofO Issued on 2/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2021 APPLICANT
Assigned to Plan Check Engineer 4/23/2021 JEROME MAGAT PALMA
Corrections Issued 4/24/2021 JEROME MAGAT PALMA
Plan Check Approved 9/28/2021 JEROME MAGAT PALMA
Issued 9/28/2021 APPLICANT
Building Plans Picked Up 9/30/2021 APPLICANT
CofO in Progress 1/12/2023 RYAN SALAZAR
Permit Finaled 2/4/2023 MICHAEL SMITH
CofO Issued 2/4/2023 MICHAEL SMITH
Permit Finaled 2/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/11/2021 ADRIAN CASTRO
ZA Case Cleared 8/30/2021 PABLO ESTRADA
Sewer availability Cleared 8/31/2021 ROSE MARIE SMITH
Low Impact Development Cleared 9/20/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/28/2021 DAGOVERTO GUERRERO

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/6/2021 Conditional Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/15/2021 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/20/2021 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 11/8/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 11/16/2021 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 11/16/2021 Partial Approval CHRISTOPHE COCHRAN
Insulation 11/19/2021 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2021 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/25/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Drywall Nailing 1/25/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/25/2022 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 1/25/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 1/25/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/25/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 2/25/2022 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 2/25/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 3/7/2022 Approved RYAN SALAZAR
Insulation 3/7/2022 Approved RYAN SALAZAR
Drywall Nailing 4/21/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 4/21/2022 Approved ASHLEY THOMPSON
Shower Pan 4/21/2022 Approved ASHLEY THOMPSON
ELECTRICAL-Final 7/29/2022 Corrections Issued RAFAEL CORTES
PLUMBING-Final 7/29/2022 Approved RAFAEL CORTES
ELECTRICAL-Final 11/29/2022 Partial Approval JOHN COLEMAN
Final 11/29/2022 Not Ready for Inspection JOHN COLEMAN
Green Building Final 11/29/2022 Corrections Issued JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Not Ready JOHN COLEMAN
Smoke Detectors 11/29/2022 Approved JOHN COLEMAN
Final 12/21/2022 Not Ready for Inspection RYAN SALAZAR
Green Building Final 12/21/2022 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Approved RYAN SALAZAR
ELECTRICAL-Final 1/12/2023 Approved RYAN SALAZAR
Final 1/12/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 1/12/2023 Approved RYAN SALAZAR
HVAC-Final 1/12/2023 Approved RYAN SALAZAR