23245 W GONZALES DR 91367
Certificate Information: 23245 W GONZALES DR 91367
- Application / Permit
- 21014-20000-01914
- Plan Check / Job No.
- B21VN04624
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 4'-11" X 9'-10" ADDITION TO AND REMODEL TO THE (E) SFD. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 7/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2021 | PARISA ZAHABI |
| Corrections Issued | 4/25/2021 | PARISA ZAHABI |
| Issued | 5/24/2021 | APPLICANT |
| Building Plans Picked Up | 5/24/2021 | APPLICANT |
| CofO in Progress | 7/11/2021 | TROY SANDERS |
| Permit Finaled | 7/19/2021 | JOHN JANSON |
| CofO Issued | 7/19/2021 | JOHN JANSON |
| Permit Finaled | 7/19/2021 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/23/2021 | PARISA ZAHABI |
| Miscellaneous | Cleared | 5/6/2021 | MIGUEL GAMBOA |
| Roof/Waste drainage to street | Cleared | 5/6/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/12/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/26/2021 | Approved | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 6/1/2021 | Approved | TROY SANDERS |
| Insulation | 6/7/2021 | No Access for Inspection | DAVID SANDOVAL |
| Insulation | 6/9/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 6/11/2021 | Approved | TROY SANDERS |
| Green Building Rough | 6/11/2021 | Approved | TROY SANDERS |
| Insulation | 6/11/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 6/11/2021 | Partial Approval | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 6/11/2021 | Approved | TROY SANDERS |
| Drywall Nailing | 6/15/2021 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 6/15/2021 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 7/9/2021 | Approved | TROY SANDERS |
| Final | 7/9/2021 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 7/9/2021 | Approved | TROY SANDERS |
| HVAC-Final | 7/9/2021 | Approved | TROY SANDERS |
| PLUMBING-Final | 7/9/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/9/2021 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 7/9/2021 | Approved | TROY SANDERS |