15231 W CANTARA ST 91402

Certificate Information: 15231 W CANTARA ST 91402

Application / Permit
21014-20000-01912
Plan Check / Job No.
B21VN04616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) ATTACHED PATIO COVER. ADD 14'-6" X 19'-9" TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/20/2021
Issuing Office
Current Status
CofO Issued on 8/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2021 APPLICANT
Assigned to Plan Check Engineer 4/26/2021 RAPHAEL ROSAS
Corrections Issued 4/26/2021 RAPHAEL ROSAS
Plan Check Approved 7/9/2021 RAPHAEL ROSAS
Building Plans Picked Up 7/9/2021 APPLICANT
Issued 7/20/2021 APPLICANT
CofO in Progress 12/11/2023 CHRISTOPHER ROJAS
Permit Finaled 8/23/2024 DANIEL ORRANTE
CofO Issued 8/23/2024 DANIEL ORRANTE
Permit Finaled 8/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/2/2021 LEE GUILBEAUX
Sewer availability Cleared 6/2/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/4/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/4/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/18/2021 Conditional Approval GREGG CUMMINGS
Footing/Foundation/Slab 8/26/2021 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 9/8/2021 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 9/10/2021 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 9/14/2021 Approved GREGG CUMMINGS
Footing/Foundation/Slab 9/14/2021 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 11/17/2021 Corrections Issued GREGG CUMMINGS
Green Building Rough 11/17/2021 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 11/17/2021 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 11/24/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 11/24/2021 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 11/24/2021 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 12/7/2021 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 12/7/2021 Approved GREGG CUMMINGS
ELECTRICAL-Rough 12/16/2021 Corrections Issued GREGG CUMMINGS
Interior/Exterior Lathing 12/21/2021 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 12/22/2021 Corrections Issued MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 12/27/2021 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 1/24/2022 Approved GREGG CUMMINGS
ELECTRICAL-Rough 1/24/2022 Approved GREGG CUMMINGS
Green Building Rough 1/24/2022 Approved GREGG CUMMINGS
HVAC-Rough 1/24/2022 Approved GREGG CUMMINGS
Insulation 1/26/2022 Corrections Issued GREGG CUMMINGS
Insulation 1/31/2022 Approved WILLIAM WREN
Drywall Nailing 2/7/2022 Approved WILLIAM WREN
Shower Pan 2/7/2022 Approved WILLIAM WREN
Final 10/24/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 10/24/2023 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 10/24/2023 Approved CHRISTOPHER ROJAS
Final 11/14/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 11/14/2023 Approved GREGG CUMMINGS
Smoke Detectors 11/14/2023 Not Ready for Inspection GREGG CUMMINGS
Final 12/5/2023 Partial Approval CHRISTOPHER ROJAS
Smoke Detectors 12/5/2023 Approved CHRISTOPHER ROJAS
Final 12/8/2023 OK to Issue CofO CHRISTOPHER ROJAS