15231 W CANTARA ST 91402
Certificate Information: 15231 W CANTARA ST 91402
- Application / Permit
- 21014-20000-01912
- Plan Check / Job No.
- B21VN04616
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) ATTACHED PATIO COVER. ADD 14'-6" X 19'-9" TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Current Status
- CofO Issued on 8/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2021 | RAPHAEL ROSAS |
| Corrections Issued | 4/26/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 7/9/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 7/9/2021 | APPLICANT |
| Issued | 7/20/2021 | APPLICANT |
| CofO in Progress | 12/11/2023 | CHRISTOPHER ROJAS |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
| CofO Issued | 8/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/2/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/2/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/4/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/18/2021 | Conditional Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/26/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/8/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/10/2021 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 9/14/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/14/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/17/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 11/17/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/17/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/24/2021 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 11/24/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 11/24/2021 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/7/2021 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 12/7/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/16/2021 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/21/2021 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/22/2021 | Corrections Issued | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2021 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/24/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/24/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 1/24/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 1/24/2022 | Approved | GREGG CUMMINGS |
| Insulation | 1/26/2022 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 1/31/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 2/7/2022 | Approved | WILLIAM WREN |
| Shower Pan | 2/7/2022 | Approved | WILLIAM WREN |
| Final | 10/24/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 10/24/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/24/2023 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/24/2023 | Approved | CHRISTOPHER ROJAS |
| Final | 11/14/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 11/14/2023 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 11/14/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 12/5/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Smoke Detectors | 12/5/2023 | Approved | CHRISTOPHER ROJAS |
| Final | 12/8/2023 | OK to Issue CofO | CHRISTOPHER ROJAS |