10235 N MATHER AVE 91040
Certificate Information: 10235 N MATHER AVE 91040
- Application / Permit
- 21014-20000-01907
- Plan Check / Job No.
- B21VN04611
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 614 SQ. FT. ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/3/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | COLIN LOREDO |
| Corrections Issued | 6/2/2021 | COLIN LOREDO |
| Quality Review Completed | 6/8/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/11/2021 | APPLICANT |
| Plan Check Approved | 12/16/2021 | COLIN LOREDO |
| Issued | 1/3/2022 | APPLICANT |
| CofO in Progress | 3/9/2023 | DAVID ANDERSON |
| Permit Finaled | 4/4/2023 | DANIEL ORRANTE |
| CofO Issued | 4/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/28/2021 | BRIAN MILLER |
| Sewer availability | Cleared | 7/7/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 12/3/2021 | ANDRES COVARRUBIAS |
| GPI Written Notices | Cleared | 12/16/2021 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Rhody Kenneth R; Lic. No.: 441339-B | 4270 CHULA SENDA LA CANADA FLINTRIDGE, CA 91011 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/18/2022 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 1/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 1/26/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/6/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 4/6/2022 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 4/6/2022 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 4/6/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 4/6/2022 | Approved | WILLIAM WREN |
| Wood Frame | 4/6/2022 | Corrections Issued | WILLIAM WREN |
| Deputy Wood Construction | 4/8/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2022 | Approved | WILLIAM WREN |
| Rough-Elec/Plmb/HVAC | 4/8/2022 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 4/15/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 4/15/2022 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 4/22/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/22/2022 | Approved | MICHEL ABAJAN |
| Insulation | 4/27/2022 | Not Ready for Inspection | WILLIAM WREN |
| Insulation | 4/28/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 5/11/2022 | Approved | WILLIAM WREN |
| Shower Pan | 5/11/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 7/22/2022 | Conditional Approval | DAVID ANDERSON |
| ELECTRICAL-Final | 10/26/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 10/26/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 10/26/2022 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Final | 10/26/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 10/26/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Not Ready | DAVID ANDERSON |
| Service/Power Release | 10/26/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 10/26/2022 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Final | 2/7/2023 | Approved | DAVID ANDERSON |
| Final | 2/7/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 2/7/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 2/7/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 2/7/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 2/7/2023 | Approved | DAVID ANDERSON |
| Final | 3/8/2023 | Corrections Issued | DAVID ANDERSON |
| Final | 3/9/2023 | OK to Issue CofO | DAVID ANDERSON |