13150-13152 W RATNER ST 91605

Certificate Information: 13150-13152 W RATNER ST 91605

Application / Permit
21014-20000-01904
Plan Check / Job No.
B21VN04607
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (400 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22. 18'-5" X 13' IRREG SHAPED ADDITION FOR ONE NEW BEDROOM AND BATHROOM.
Permit Issued
Issued on 6/25/2021
Issuing Office
Current Status
CofO Issued on 4/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 JEROME MAGAT PALMA
Corrections Issued 4/22/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 6/2/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 6/21/2021 JEROME MAGAT PALMA
Plan Check Approved 6/25/2021 JEROME MAGAT PALMA
Issued 6/25/2021 APPLICANT
Building Plans Picked Up 7/8/2021 APPLICANT
CofO in Progress 10/31/2022 GREGG CUMMINGS
No Progress 11/19/2022 MICHAEL SMITH
CofO in Progress 12/6/2022 DAVID MATSON
CofO in Progress 4/13/2023 MICHAEL SMITH
CofO Issued 4/13/2023 MICHAEL SMITH
Permit Finaled 4/13/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/7/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/8/2021 GABRIEL ROBLES
Sewer availability Cleared 6/24/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/27/2021 Corrections Issued GREGG CUMMINGS
Pre-Inspection 10/27/2021 Approved GREGG CUMMINGS
Deputy Drilled-In Anchors 12/17/2021 Approved GREGG CUMMINGS
Gas Test 12/17/2021 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 1/3/2022 Not Ready for Inspection GREGG CUMMINGS
Gas Test 1/3/2022 Not Ready for Inspection GREGG CUMMINGS
Gas Test 1/4/2022 Partial Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/4/2022 SGSOV Not Ready GREGG CUMMINGS
Footing/Foundation/Slab 1/6/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 1/25/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 1/27/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 1/27/2022 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 1/27/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 1/27/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 3/14/2022 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 3/14/2022 Corrections Issued WILLIAM WREN
HVAC-Rough 3/14/2022 Approved WILLIAM WREN
PLUMBING-Rough 3/14/2022 Corrections Issued WILLIAM WREN
BUILDING-Rough-Frame 3/23/2022 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 3/23/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 3/23/2022 Approved GREGG CUMMINGS
Green Building Rough 3/23/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 3/23/2022 Partial Approval GREGG CUMMINGS
Rough-Elec/Plmb/HVAC 3/23/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 4/21/2022 Corrections Issued GREGG CUMMINGS
Sewer 4/21/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 4/25/2022 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 4/25/2022 Partial Approval GREGG CUMMINGS
Green Building Rough 4/25/2022 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 4/25/2022 Partial Approval GREGG CUMMINGS
Insulation 5/5/2022 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 5/5/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Partial Approval GREGG CUMMINGS
Drywall Nailing 6/2/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 6/2/2022 Approved WILLIAM WREN
Shower Pan 6/2/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 6/16/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 7/13/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 7/13/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 7/13/2022 Partial Approval GREGG CUMMINGS
Green Building Rough 7/13/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 7/13/2022 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 7/27/2022 Approved WILLIAM WREN
Green Building Rough 7/27/2022 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 7/27/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/3/2022 Approved GREGG CUMMINGS
Green Building Rough 8/3/2022 Approved GREGG CUMMINGS
HVAC-Rough 8/3/2022 Approved GREGG CUMMINGS
Insulation 8/3/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 8/3/2022 Partial Approval GREGG CUMMINGS
Drywall Nailing 8/10/2022 Approved WILLIAM WREN
Shower Pan 8/10/2022 Not Ready for Inspection WILLIAM WREN
Interior/Exterior Lathing 8/26/2022 Approved GREGG CUMMINGS
Shower Pan 8/26/2022 Corrections Issued GREGG CUMMINGS
Shower Pan 8/30/2022 Approved MICHEL ABAJAN
Final 10/17/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 10/17/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 10/17/2022 Approved GREGG CUMMINGS
Final 10/26/2022 Conditional Approval GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Approved GREGG CUMMINGS
Final 12/7/2022 Corrections Issued GREGG CUMMINGS