8201 N WOODLEY AVE 91406
Certificate Information: 8201 N WOODLEY AVE 91406
- Application / Permit
- 21014-20000-01899
- Plan Check / Job No.
- B21VN04592
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- STORAGE MEZZANINE ADDITION WITHIN THE (E) WAREHOUSE. SEE COMMENTS
- Permit Issued
- Issued on 8/5/2021
- Issuing Office
- Current Status
- CofO Issued on 10/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | MARVEL DELACRUZ |
| Corrections Issued | 5/1/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 5/5/2021 | STEVEN KIM |
| Applicant returned to address corrections | 7/2/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 7/27/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 7/29/2021 | MARVEL DELACRUZ |
| Issued | 8/5/2021 | APPLICANT |
| CofO in Progress | 10/9/2025 | DEANDRE HOFFMAN |
| Permit Finaled | 10/10/2025 | JEFFREY DURAN |
| Permit Finaled | 10/10/2025 | JEFFREY DURAN |
| CofO Issued | 10/10/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Green Code | Cleared | 7/1/2021 | MICHAEL AYERS |
| DAS Clearance | Cleared | 7/6/2021 | MARVEL DELACRUZ |
| ZA Case | Cleared | 7/13/2021 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/14/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Fridlund,, David John; Lic. No.: C20787 | 1917 SILVER WOOD LANE LOS ANGELES, CA 90041 |
| Contractor | Sigbjorn Group; Lic. No.: 363989-B | 954 W BATAVIA ORANGE, CA 92867 |
| Engineer | Boros,, Janos; Lic. No.: C54869 | 14189 FOOTHILL BLVD STE 101 FONTANA, CA 92335 |
| Engineer | Fateen,, Sal Eldin; Lic. No.: C25969 | 1130 E CYPRESS STREET COVINA, CA 91724 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/17/2021 | No Access for Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 9/20/2021 | Conditional Approval | JEFFREY FULTON |
| Footing/Foundation/Slab | 9/24/2021 | Partial Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 9/28/2021 | Partial Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Partial Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2021 | Partial Inspection | JEFFREY FULTON |
| Final | 12/10/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 12/10/2021 | Approved | JEFFREY FULTON |
| Green Building Final | 12/10/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Rough | 12/10/2021 | Approved | JEFFREY FULTON |
| Reinforced Masonry Frame | 12/10/2021 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 12/10/2021 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 12/10/2021 | Approved | JEFFREY FULTON |
| Final | 1/14/2022 | OK to Issue CofO | JEFFREY FULTON |
| Green Building Final | 1/14/2022 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 1/14/2022 | SGSOV Approved | JEFFREY FULTON |
| Pre-Inspection | 10/8/2025 | Approved | DEANDRE HOFFMAN |