20356 W BALTAR ST 91306
Certificate Information: 20356 W BALTAR ST 91306
- Application / Permit
- 21014-20000-01893
- Plan Check / Job No.
- B21VN04582
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 22'-10" X 39'-1", 3'-2.5" X 6'-4", AND 4' X 13' ADDITIONS AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | RAPHAEL ROSAS |
| Corrections Issued | 4/24/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 8/18/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 8/30/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 9/2/2021 | APPLICANT |
| Issued | 4/13/2022 | APPLICANT |
| CofO in Progress | 3/7/2024 | ALEXANDER HANDY |
| Permit Finaled | 11/19/2024 | JOHN JANSON |
| CofO Issued | 11/19/2024 | JOHN JANSON |
| Permit Finaled | 11/19/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/27/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 8/12/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/13/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16200 VENTURA BLVD STE 317 ENCINO, CA 91436 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/22/2022 | Conditional Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 4/27/2022 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 4/27/2022 | Not Ready for Inspection | STEVEN BACK |
| Deputy Reinf. Concrete | 4/29/2022 | Conditional Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 5/3/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 5/3/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 5/16/2022 | Partial Approval | STEVEN BACK |
| Insulation | 5/16/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 5/16/2022 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 5/19/2022 | Partial Approval | STEVEN BACK |
| Insulation | 5/19/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 5/19/2022 | Partial Approval | STEVEN BACK |
| Deputy Wood Construction | 6/8/2022 | Conditional Approval | STEVEN BACK |
| Final | 6/13/2022 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/14/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 7/14/2022 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 7/14/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 9/22/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 9/22/2022 | Approved | STEVEN BACK |
| Green Building Rough | 9/22/2022 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 9/22/2022 | Approved | STEVEN BACK |
| Green Building Rough | 9/28/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/28/2022 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 10/6/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 10/24/2022 | Approved | HENRY KIM |
| Smoke Detectors | 10/24/2022 | Corrections Issued | HENRY KIM |
| Shower Pan | 11/2/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 11/18/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 3/6/2024 | Approved | ALEXANDER HANDY |
| Final | 3/6/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 3/6/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 3/6/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/6/2024 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/6/2024 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 3/6/2024 | Approved | ALEXANDER HANDY |