5854 N LEMP AVE 91601
Certificate Information: 5854 N LEMP AVE 91601
- Application / Permit
- 21014-20000-01885
- Plan Check / Job No.
- B21VN04564
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 1149.58 ADDITION TO REAR OF EXISTING 1-STORY SINGLE FAMILY DWELLING AND 62.55 SQFT ENCLOSURE TO FRONT OF (E) SFD WITH ATTACHED GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED
- Permit Issued
- Issued on 11/8/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | ALYSSA N NARCISO |
| Corrections Issued | 5/26/2021 | ALYSSA N NARCISO |
| Quality Review Completed | 5/27/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/1/2021 | APPLICANT |
| Plan Check Approved | 10/28/2021 | PETER MOSESIAN |
| Issued | 11/8/2021 | APPLICANT |
| CofO in Progress | 8/15/2022 | THOMAS FINNILA |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
| CofO Issued | 8/27/2022 | MICHAEL SMITH |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/20/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/18/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 9/21/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 10/4/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/19/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/22/2021 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/6/2021 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/6/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 12/8/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/13/2021 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/13/2021 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/13/2021 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/15/2021 | Partial Approval | THOMAS FINNILA |
| Deputy Wood Construction | 2/7/2022 | Conditional Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 2/11/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 2/11/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 2/15/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/17/2022 | Approved | RICHARD DOCKUS |
| Shower Pan | 2/17/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 2/23/2022 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/1/2022 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 3/3/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/3/2022 | Partial Approval | MISAEL ESPARZA |
| Insulation | 3/7/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 3/11/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 7/26/2022 | Approved | CALEB MEISTER |
| HVAC-Final | 7/26/2022 | Approved | CALEB MEISTER |
| PLUMBING-Final | 7/26/2022 | Approved | CALEB MEISTER |
| Service/Power Release | 7/26/2022 | Not Ready for Inspection | CALEB MEISTER |
| Smoke Detectors | 7/26/2022 | Approved | CALEB MEISTER |
| Green Building Final | 8/9/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 8/12/2022 | OK to Issue CofO | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Approved | THOMAS FINNILA |