16136 W RINALDI ST 91344
Certificate Information: 16136 W RINALDI ST 91344
- Application / Permit
- 21014-20000-01874
- Plan Check / Job No.
- B21VN04550
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 21' DETACHED GARAGE AND ADD 22' X 40' IRREGULAR SHAPE TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Current Status
- CofO Issued on 12/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | RAPHAEL ROSAS |
| Corrections Issued | 4/22/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/30/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/13/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 4/13/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/14/2022 | APPLICANT |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 12/3/2024 | JAVIER RAMOS JR |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
| CofO Issued | 12/4/2024 | RUBEN SALAS |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/26/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/20/2021 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 1/13/2022 | JOHN BACON |
| Grading Pre-Inspection | Cleared | 1/13/2022 | RAPHAEL ROSAS |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/17/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/9/2024 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 5/15/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/31/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/12/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/12/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 6/12/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/12/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/12/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/2/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/2/2024 | Approved | VINCENT HANLEY |
| Insulation | 7/2/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/2/2024 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 7/9/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/9/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 8/12/2024 | Approved | JAVIER RAMOS JR |
| Final | 9/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 9/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/9/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 9/9/2024 | Approved | JENNIFER RABUCHIN |
| Final | 11/18/2024 | Conditional Approval | JENNIFER RABUCHIN |
| Green Building Final | 11/18/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Final | 12/3/2024 | OK to Issue CofO | JAVIER RAMOS JR |