16136 W RINALDI ST 91344

Certificate Information: 16136 W RINALDI ST 91344

Application / Permit
21014-20000-01874
Plan Check / Job No.
B21VN04550
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 21' DETACHED GARAGE AND ADD 22' X 40' IRREGULAR SHAPE TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 5/2/2022
Issuing Office
Current Status
CofO Issued on 12/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/21/2021 RAPHAEL ROSAS
Corrections Issued 4/22/2021 RAPHAEL ROSAS
Applicant returned to address corrections 12/30/2021 RAPHAEL ROSAS
Applicant returned to address corrections 1/13/2022 RAPHAEL ROSAS
Plan Check Approved 4/13/2022 RAPHAEL ROSAS
Building Plans Picked Up 4/14/2022 APPLICANT
Issued 5/2/2022 APPLICANT
CofO in Progress 12/3/2024 JAVIER RAMOS JR
Permit Finaled 12/4/2024 RUBEN SALAS
CofO Issued 12/4/2024 RUBEN SALAS
Permit Finaled 12/4/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/26/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/26/2021 LEE GUILBEAUX
Sewer availability Cleared 12/20/2021 LEE GUILBEAUX
Construction near power lines Cleared 1/13/2022 JOHN BACON
Grading Pre-Inspection Cleared 1/13/2022 RAPHAEL ROSAS
Roof/Waste drainage to street Cleared 4/4/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/17/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 5/9/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 5/15/2024 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 5/31/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/12/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/12/2024 Approved JAVIER RAMOS JR
Green Building Rough 6/12/2024 Approved JAVIER RAMOS JR
HVAC-Rough 6/12/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/12/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/2/2024 Approved VINCENT HANLEY
Green Building Rough 7/2/2024 Approved VINCENT HANLEY
Insulation 7/2/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/2/2024 Partial Approval VINCENT HANLEY
Drywall Nailing 7/9/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/9/2024 Approved JAVIER RAMOS JR
Underground Mechanical 8/12/2024 Approved JAVIER RAMOS JR
Final 9/9/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 9/9/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 9/9/2024 Approved JENNIFER RABUCHIN
Final 11/18/2024 Conditional Approval JENNIFER RABUCHIN
Green Building Final 11/18/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Approved JENNIFER RABUCHIN
Final 12/3/2024 OK to Issue CofO JAVIER RAMOS JR