11718 W HUSTON ST 91607

Certificate Information: 11718 W HUSTON ST 91607

Application / Permit
21014-20000-01873
Plan Check / Job No.
B21VN04548
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 14' X 18' (E) DETACHED GARAGE AND ADD 14'-9" X 16'-5" TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/13/2021
Issuing Office
Valley
Current Status
CofO Issued on 7/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/21/2021 RAPHAEL ROSAS
Corrections Issued 4/22/2021 RAPHAEL ROSAS
Applicant returned to address corrections 6/22/2021 RAPHAEL ROSAS
Plan Check Approved 7/2/2021 RAPHAEL ROSAS
Building Plans Picked Up 8/10/2021 APPLICANT
Issued 8/13/2021 APPLICANT
CofO in Progress 7/15/2022 THOMAS FINNILA
CofO in Progress 7/15/2022 THOMAS FINNILA
CofO Issued 7/20/2022 MICHAEL SMITH
Permit Finaled 7/20/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/17/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/17/2021 CARLOS AGUILERA
Sewer availability Cleared 5/24/2021 CARLOS AGUILERA
Specific Plan Cleared 6/10/2021 CORREY KITCHENS
ZI Cleared 6/10/2021 CORREY KITCHENS
ZI Cleared 6/10/2021 CORREY KITCHENS
Eng Process Fee Ord 176,300 Cleared 6/25/2021 CARLOS AGUILERA

Contact Information

Contractor J G & J Construction; Lic. No.: 689305-B 13348 BORDEN AVE      SYLMAR, CA 91342
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/23/2021 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/1/2021 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 9/17/2021 Approved JENNIFER RABUCHIN
Gas Test 9/17/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 9/17/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 11/1/2021 Partial Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/1/2021 Partial Approval THOMAS FINNILA
PLUMBING-Rough 11/1/2021 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 11/2/2021 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 11/15/2021 Partial Approval THOMAS FINNILA
Green Building Rough 11/15/2021 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 11/18/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 11/23/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 11/23/2021 Approved THOMAS FINNILA
Green Building Rough 11/23/2021 Approved THOMAS FINNILA
PLUMBING-Rough 11/23/2021 Approved THOMAS FINNILA
Insulation 11/29/2021 Approved THOMAS FINNILA
Drywall Nailing 12/8/2021 Approved MISAEL ESPARZA
Final 4/27/2022 Corrections Issued DAVID MATSON
Green Building Final 4/27/2022 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 4/27/2022 SGSOV Approved DAVID MATSON
Smoke Detectors 4/27/2022 Approved DAVID MATSON
Final 5/18/2022 Partial Approval THOMAS FINNILA
Final 7/15/2022 OK to Issue CofO THOMAS FINNILA