5438 N WOODMAN AVE 91401
Certificate Information: 5438 N WOODMAN AVE 91401
- Application / Permit
- 21014-20000-01872
- Plan Check / Job No.
- B21VN04545
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d). ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION.
- Permit Issued
- Issued on 6/23/2021
- Issuing Office
- Current Status
- CofO Issued on 4/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2021 | SERGIO MUNIZ |
| Assigned to Plan Check Engineer | 4/28/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 4/28/2021 | SERGIO MUNIZ |
| Corrections Issued | 4/29/2021 | SERGIO MUNIZ |
| Plan Check Approved | 6/8/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 6/10/2021 | APPLICANT |
| Plan Check Approved | 6/22/2021 | JEFFREY TANGONAN |
| Issued | 6/23/2021 | APPLICANT |
| CofO in Progress | 4/12/2025 | RAUL OLAGI |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
| CofO Issued | 4/15/2025 | RUBEN SALAS |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 5/24/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/3/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 7/22/2021 | Corrections Issued | CHARLES POWELL |
| Footing/Foundation/Slab | 8/10/2021 | Partial Approval | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 8/23/2021 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/19/2021 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 11/15/2021 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 11/15/2021 | Corrections Issued | ALAN MORELOS |
| ELECTRICAL-Rough | 11/23/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 11/23/2021 | Partial Approval | RICHARD DOCKUS |
| Pre-Inspection | 12/14/2021 | Partial Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/17/2021 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 1/21/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 1/21/2022 | Approved | RICHARD DOCKUS |
| Insulation | 1/21/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 1/21/2022 | Partial Approval | RICHARD DOCKUS |
| Rough-Elec/Plmb/HVAC | 1/21/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 2/1/2022 | Approved | ALAN MORELOS |
| Final | 4/21/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 4/21/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/21/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 4/21/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 7/19/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 7/19/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 7/19/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 8/22/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 8/22/2022 | Approved | RICHARD DOCKUS |
| Final | 8/29/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 8/29/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | RICHARD DOCKUS |
| Final | 4/11/2025 | OK to Issue CofO | RAUL OLAGI |