5722 1/2 S WILTON PL 90062

Certificate Information: 5722 1/2 S WILTON PL 90062

Application / Permit
21014-20000-01868
Plan Check / Job No.
B21VN04536
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
15' X 17'-7" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/15/2021
Issuing Office
Current Status
CofO Issued on 12/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Assigned to Plan Check Engineer 4/23/2021 JEROME MAGAT PALMA
Corrections Issued 4/24/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 7/19/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 9/1/2021 JEROME MAGAT PALMA
Plan Check Approved 9/28/2021 JEROME MAGAT PALMA
Building Plans Picked Up 9/30/2021 APPLICANT
Issued 10/15/2021 APPLICANT
CofO in Progress 12/16/2023 JOAQUIN GREENOUGH
CofO Issued 12/22/2023 DEROLD HAUFF
Permit Finaled 12/22/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/28/2021 JEANIE LAM
Address approval Cleared 5/10/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/11/2021 JEANIE LAM
Sewer availability Cleared 5/11/2021 JEANIE LAM
CPC Cleared 9/17/2021 RICHARD REASER
ZA Case Cleared 9/17/2021 RICHARD REASER

Contact Information

Contractor Molina Builders Inc; Lic. No.: 1063589-B 15061 ARCHWOOD ST APT 6      VAN NUYS, CA 91405

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/27/2021 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 3/1/2022 Partial Approval SABAS ALONSO
Pre-Inspection 3/1/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 3/7/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 3/9/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 3/14/2022 Partial Approval SABAS ALONSO
Underground Mechanical 3/14/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 3/16/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 5/10/2022 Not Ready for Inspection SABAS ALONSO
Green Building Rough 5/10/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 6/3/2022 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Approved ANTHONY EGSON
Green Building Rough 6/3/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 6/3/2022 Not Ready for Inspection ANTHONY EGSON
Special/Order Compliance 6/27/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 7/2/2022 Conditional Approval RICHARD ROBLES
Interior/Exterior Lathing 7/8/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 9/7/2022 Approved SABAS ALONSO
Green Building Rough 9/7/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 9/7/2022 Not Ready for Inspection SABAS ALONSO
Sewer 9/15/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 9/30/2022 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 12/1/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 12/1/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 12/1/2022 Approved SABAS ALONSO
Green Building Rough 12/1/2022 Corrections Issued SABAS ALONSO
HVAC-Rough 12/1/2022 Approved SABAS ALONSO
PLUMBING-Final 12/1/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 12/1/2022 Approved SABAS ALONSO
Underground Mechanical 12/1/2022 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 12/9/2022 Not Ready for Inspection SABAS ALONSO
Green Building Rough 12/9/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 12/20/2022 Approved SABAS ALONSO
Insulation 12/20/2022 Approved SABAS ALONSO
Drywall Nailing 2/27/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 7/12/2023 Approved SABAS ALONSO
Final 7/12/2023 Corrections Issued SABAS ALONSO
Green Building Final 7/12/2023 Corrections Issued SABAS ALONSO
Green Building Rough 7/12/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/12/2023 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 7/12/2023 Approved SABAS ALONSO
ELECTRICAL-Final 10/20/2023 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 10/20/2023 Approved JUSTIN HAWLEY
Final 10/20/2023 Not Ready for Inspection JUSTIN HAWLEY
Gas Test 10/20/2023 Approved JUSTIN HAWLEY
Green Building Final 10/20/2023 Approved JUSTIN HAWLEY
PLUMBING-Final 10/20/2023 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 10/20/2023 SGSOV Approved JUSTIN HAWLEY
Service/Power Release 10/20/2023 Approved JUSTIN HAWLEY
Final 10/30/2023 Corrections Issued CRAIG DAVIS
Final 12/1/2023 Corrections Issued CRAIG DAVIS
Final 12/6/2023 Corrections Issued CRAIG DAVIS
Final 12/15/2023 OK to Issue CofO JOAQUIN GREENOUGH