3009 S 5TH AVE 90018
Certificate Information: 3009 S 5TH AVE 90018
- Application / Permit
- 21014-20000-01851
- Plan Check / Job No.
- B21VN04472
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (22'-0" x 23'-6") IRR. SHAPE BEDROOM,WITH CLOSET AND FULL BATHROOM & STUDY ROOM TO THE (E) ONE-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 7/18/2022
- Issuing Office
- Current Status
- CofO Issued on 1/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2021 | TROY DEGUZMAN |
| Corrections Issued | 4/19/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 5/17/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 7/2/2021 | TROY DEGUZMAN |
| Plan Check Approved | 7/15/2022 | PINANK PATEL |
| Issued | 7/18/2022 | APPLICANT |
| Building Plans Picked Up | 7/19/2022 | APPLICANT |
| CofO in Progress | 3/6/2024 | JUSTIN HAWLEY |
| Permit Finaled | 1/2/2025 | DEROLD HAUFF |
| CofO Issued | 1/2/2025 | DEROLD HAUFF |
| Permit Finaled | 1/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/21/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 4/27/2021 | WALLIE JONG |
| HPOZ | Cleared | 7/5/2022 | DANIEL MATA |
| ZI | Cleared | 7/5/2022 | DANIEL MATA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Ing Construction & Inv; Lic. No.: 961589-B | 5627 SEPULVEDA BOULEVARD # 208 VAN NUYS, CA 91411 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/17/2023 | Conditional Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 1/18/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 2/6/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 2/6/2023 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 2/6/2023 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 2/6/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/9/2023 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2023 | Partial Approval | CALEB MEISTER |
| Insulation | 2/9/2023 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 5/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 5/15/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 5/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 5/15/2023 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 5/15/2023 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 7/7/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 7/12/2023 | Approved | CALEB MEISTER |
| Shower Pan | 7/12/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 7/26/2023 | Approved | CALEB MEISTER |
| Final | 11/1/2023 | Conditional Approval | STUART CHAPMAN |
| Green Building Final | 11/1/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 11/1/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 3/5/2024 | Approved | STUART CHAPMAN |
| Final | 3/5/2024 | Conditional Approval | STUART CHAPMAN |
| HVAC-Final | 3/5/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 3/5/2024 | Approved | STUART CHAPMAN |
| Service/Power Release | 3/5/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 3/6/2024 | Approved | JUSTIN HAWLEY |
| Final | 3/6/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 3/6/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 3/6/2024 | Approved | JUSTIN HAWLEY |