14808 W HARTLAND ST 91405
Certificate Information: 14808 W HARTLAND ST 91405
- Application / Permit
- 21014-20000-01849
- Plan Check / Job No.
- B21VN04467
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT WITH 2ND STORY ADDITION (20'-0"X35'-6") PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/21/2021
- Issuing Office
- Current Status
- CofO Issued on 4/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 6/1/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 6/9/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/11/2021 | APPLICANT |
| Plan Check Approved | 10/20/2021 | MOHAMMAD ESMAILI |
| Issued | 10/21/2021 | APPLICANT |
| CofO in Progress | 3/26/2024 | RYAN SALAZAR |
| Permit Finaled | 4/15/2024 | DANIEL ORRANTE |
| CofO Issued | 4/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/14/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 8/20/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 9/30/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 9/30/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/11/2022 | Approved | RICHARD DOCKUS |
| Pre-Inspection | 10/7/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 6/2/2023 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/2/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/2/2023 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/20/2023 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 6/20/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Light Gage Steel Frame | 6/20/2023 | Partial Inspection | RYAN SALAZAR |
| Reinforced Concrete Frame | 6/20/2023 | Partial Inspection | RYAN SALAZAR |
| Reinforced Masonry Frame | 6/20/2023 | Partial Inspection | RYAN SALAZAR |
| Structural Steel Frame | 6/20/2023 | Partial Inspection | RYAN SALAZAR |
| Wood Frame | 6/20/2023 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 6/29/2023 | Approved | RYAN SALAZAR |
| Deputy Wood Construction | 7/18/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/16/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 8/16/2023 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 8/16/2023 | Approved | RYAN SALAZAR |
| Wood Frame | 8/16/2023 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/21/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/21/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/21/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 9/21/2023 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 9/21/2023 | Approved | RYAN SALAZAR |
| Wood Frame | 9/21/2023 | Approved | RYAN SALAZAR |
| Insulation | 9/29/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 9/29/2023 | Approved | RYAN SALAZAR |
| Pre-Inspection | 10/4/2023 | Partial Inspection | RYAN SALAZAR |
| Shower Pan | 10/4/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 3/22/2024 | Approved | RYAN SALAZAR |
| Final | 3/22/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 3/22/2024 | Approved | RYAN SALAZAR |
| HVAC-Final | 3/22/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 3/22/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 3/22/2024 | Approved | RYAN SALAZAR |
| Smoke Detectors | 3/22/2024 | Approved | RYAN SALAZAR |