11743 N CHIVERS AVE 91331
Certificate Information: 11743 N CHIVERS AVE 91331
- Application / Permit
- 21014-20000-01833
- Plan Check / Job No.
- B21VN04394
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 515 SQ. FT. ADDITION (42'-11"x12'-0") TO THE REAR OF THE (E) SFD. A NEW MASTER BEDROOM, BATHROOM, WALK IN COSET, BEDROOM AND LAUNDRY.
- Permit Issued
- Issued on 10/18/2021
- Issuing Office
- Current Status
- CofO Issued on 1/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2021 | PETER MOSESIAN |
| Corrections Issued | 4/16/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| Issued | 10/18/2021 | APPLICANT |
| CofO in Progress | 11/3/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 1/23/2024 | RUBEN SALAS |
| CofO Issued | 1/23/2024 | RUBEN SALAS |
| Permit Finaled | 1/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 5/18/2021 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/18/2021 | CARLOS AGUILERA |
| ZI | Cleared | 5/18/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 7/23/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 10/1/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/4/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 10/25/2021 | Partial Inspection | MICHEL ABAJAN |
| Pre-Inspection | 10/25/2021 | Partial Inspection | MICHEL ABAJAN |
| Grading Pre-Inspection | 12/10/2021 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 12/10/2021 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 12/10/2021 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 1/5/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/5/2022 | Corrections Issued | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 1/6/2022 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 1/10/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2022 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/1/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 4/1/2022 | Partial Inspection | MICHEL ABAJAN |
| HVAC-Rough | 4/1/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 4/1/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/1/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/7/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/7/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 4/7/2022 | Approved | MICHEL ABAJAN |
| Insulation | 4/22/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/22/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/11/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 5/12/2022 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 5/17/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/12/2023 | Approved | MICHEL ABAJAN |
| Final | 6/12/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 6/12/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/12/2023 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 6/12/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/12/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 6/12/2023 | Approved | MICHEL ABAJAN |
| Final | 11/2/2023 | OK to Issue CofO | JENNIFER RABUCHIN |