9600 N AMBOY AVE 91331
Certificate Information: 9600 N AMBOY AVE 91331
- Application / Permit
- 21014-20000-01831
- Plan Check / Job No.
- B21VN04392
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 40'-3" X 47'-8" IRREGULAR SHAPED ADDITION AND REMODEL TO (E) SFD W/ ATTACHED 11'-3" X 25'-5" PATIO COVER. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Current Status
- CofO Issued on 10/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2021 | RAPHAEL ROSAS |
| Corrections Issued | 4/19/2021 | RAPHAEL ROSAS |
| Issued | 5/3/2022 | APPLICANT |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| CofO in Progress | 8/28/2023 | MICHEL ABAJAN |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
| CofO Issued | 10/13/2023 | RUBEN SALAS |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/26/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 8/26/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/30/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 2/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Elite Remodeling & Development Inc; Lic. No.: 975264-B | 8949 RESEDA BLVD STE #217 NORTHRIDGE, CA 91324 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/22/2022 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 8/2/2022 | Partial Approval | MICHEL ABAJAN |
| Sewer | 8/2/2022 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 9/7/2022 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 11/18/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/24/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/24/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/24/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/24/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/24/2023 | Approved | MICHEL ABAJAN |
| Insulation | 4/28/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/28/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 4/28/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/3/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/3/2023 | Approved | MICHEL ABAJAN |
| Final | 7/27/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/27/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/27/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/28/2023 | Approved | MICHEL ABAJAN |
| Final | 8/28/2023 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 8/28/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 8/28/2023 | Approved | MICHEL ABAJAN |