16627 W GILMORE ST 91406
Certificate Information: 16627 W GILMORE ST 91406
- Application / Permit
- 21014-20000-01793
- Plan Check / Job No.
- B21VN04313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 9' X 9'-6" ENTRY PORCH(SKYLIGHT), CONVERT THE 11'-11"X 14'-5 1/4" REAR PATIO INTO HABITABLE SPACE, MAJOR REMODELING OF THE (E) SFD. RELOCATE THE BEDROOM AND BATHROOM, NEW INTERIOR WALLS, NEW WINDOWS, DOORS AND A SKYLIGHT AND REPLACE ALL (E) WINDOWS. FIRE SPRINKLER NFPA -13D THRU-OUT.
- Permit Issued
- Issued on 6/7/2021
- Issuing Office
- Current Status
- CofO Issued on 3/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | PARISA ZAHABI |
| Corrections Issued | 4/21/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 5/12/2021 | PARISA ZAHABI |
| Issued | 6/7/2021 | APPLICANT |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| CofO in Progress | 3/3/2023 | RAUL OLAGI |
| CofO Issued | 3/7/2023 | MICHAEL SMITH |
| Permit Finaled | 3/7/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| CPC | Cleared | 4/26/2021 | PABLO ESTRADA |
| ZI | Cleared | 4/26/2021 | PABLO ESTRADA |
| Roof/Waste drainage to street | Cleared | 5/3/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/3/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2021 | GABRIEL ROBLES |
Contact Information
| Architect | Belak-Berger,, Charles Peter; Lic. No.: C13657 | 521 W. ROSECRANS AVE. GARDENA, CA 902481514 |
| Contractor | Raw Development Inc; Lic. No.: 989611-B | 4859 W SLAUSON AVENUE #377 LOS ANGELES, CA 90056 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/16/2021 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 10/15/2021 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/19/2021 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/21/2021 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 10/21/2021 | Approved | RAUL OLAGI |
| Deputy Wood Construction | 11/15/2021 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2021 | Partial Approval | ALAN MORELOS |
| Pre-Inspection | 11/23/2021 | Partial Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 12/15/2021 | Approved | RAUL OLAGI |
| HVAC-Rough | 12/15/2021 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/11/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 1/11/2022 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 1/21/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 1/21/2022 | Approved | RAUL OLAGI |
| Insulation | 1/28/2022 | Approved | ALAN MORELOS |
| Shower Pan | 1/28/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 2/15/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 2/15/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 2/15/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 2/15/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 2/22/2022 | Approved | RYAN SALAZAR |
| Final | 2/9/2023 | No Access for Inspection | RAUL OLAGI |
| Green Building Final | 2/9/2023 | No Access for Inspection | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/9/2023 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 2/9/2023 | No Access for Inspection | RAUL OLAGI |
| Final | 2/13/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 2/13/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/13/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 2/13/2023 | Approved | RAUL OLAGI |
| Final | 3/3/2023 | OK to Issue CofO | RAUL OLAGI |