6246 N SHIRLEY AVE 91335
Certificate Information: 6246 N SHIRLEY AVE 91335
- Application / Permit
- 21014-20000-01790
- Plan Check / Job No.
- B21VN04306
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 7' X 14' ADDITION TO AND CONVET THE 20' X 20' (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 9/22/2021
- Issuing Office
- Current Status
- CofO Issued on 10/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | PARISA ZAHABI |
| Corrections Issued | 4/19/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| Plan Check Approved | 9/21/2021 | PARISA ZAHABI |
| Issued | 9/22/2021 | APPLICANT |
| CofO in Progress | 10/4/2022 | TROY SANDERS |
| Permit Finaled | 10/20/2022 | JOHN JANSON |
| CofO Issued | 10/20/2022 | JOHN JANSON |
| Permit Finaled | 10/20/2022 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/26/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/26/2021 | RIDWAN HARDY |
| Address approval | Cleared | 8/10/2021 | GABRIEL ROBLES |
| CPC | Cleared | 8/10/2021 | PABLO ESTRADA |
| Roof/Waste drainage to street | Cleared | 8/10/2021 | GABRIEL ROBLES |
| ZI | Cleared | 8/10/2021 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/11/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/25/2022 | Partial Approval | STEVEN BACK |
| Sewer | 1/25/2022 | Approved | STEVEN BACK |
| Underground Mechanical | 1/25/2022 | Approved | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 5/2/2022 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 5/10/2022 | Approved | STEVEN BACK |
| Pre-Inspection | 5/10/2022 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 5/26/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 5/26/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 6/9/2022 | Approved | STEVEN BACK |
| Green Building Rough | 6/9/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 6/9/2022 | Approved | STEVEN BACK |
| Insulation | 6/9/2022 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 6/9/2022 | Approved | STEVEN BACK |
| Shower Pan | 6/9/2022 | Approved | STEVEN BACK |
| Insulation | 7/8/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 7/13/2022 | Approved | STEVEN BACK |
| Final | 9/7/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 9/7/2022 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 9/7/2022 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 9/7/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 9/26/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 10/3/2022 | Approved | TROY SANDERS |
| Final | 10/3/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 10/3/2022 | Approved | TROY SANDERS |
| HVAC-Final | 10/3/2022 | Approved | TROY SANDERS |