13406 W FRIAR ST 91401

Certificate Information: 13406 W FRIAR ST 91401

Application / Permit
21014-20000-01786
Plan Check / Job No.
B21VN04289
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE UNDER EXISTING ROOF TO ENLARGE EX LIVING RM (9'6"X4'1") & ADD NEW FRONT ROOFED PORCH (10'X3'11").
Permit Issued
Issued on 5/18/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2021 APPLICANT
Assigned to Plan Check Engineer 5/4/2021 HAYATO TSUCHIYA
Corrections Issued 5/4/2021 HAYATO TSUCHIYA
Plan Check Approved 5/18/2021 HAYATO TSUCHIYA
Issued 5/18/2021 APPLICANT
Building Plans Picked Up 6/2/2021 APPLICANT
CofO in Progress 12/26/2021 CHRISTOPHE COCHRAN
Permit Finaled 3/11/2022 RONALD MYRICK
CofO Issued 3/11/2022 RONALD MYRICK
Permit Finaled 3/11/2022 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/7/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/14/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/19/2021 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/1/2021 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/12/2021 Partial Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Not Ready for Inspection ASHLEY THOMPSON
Footing/Foundation/Slab 10/25/2021 Partial Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/3/2021 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 11/3/2021 Approved CHRISTOPHE COCHRAN
Green Building Rough 11/3/2021 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/17/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/17/2021 Approved CHRISTOPHE COCHRAN
Drywall Nailing 12/2/2021 Approved CHRISTOPHE COCHRAN
Insulation 12/2/2021 Approved CHRISTOPHE COCHRAN
Final 12/9/2021 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 12/9/2021 Approved CHRISTOPHE COCHRAN
Smoke Detectors 12/9/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 12/23/2021 OK to Issue CofO CHRISTOPHE COCHRAN
Smoke Detectors 12/23/2021 Approved CHRISTOPHE COCHRAN