20453 W RODAX ST 91306
Certificate Information: 20453 W RODAX ST 91306
- Application / Permit
- 21014-20000-01766
- Plan Check / Job No.
- B21VN04248
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED FIRE DAMAGED FRAMING REPAIR WITHIN EX KITCHEN, DINING, LAUNDRY, BATH, BEDRM AREA PER PLAN (REMOVE & REPLACE FIXTURES & COUNTERS AT SAME LOCATION AS EXISTED). CONVERT EX ATT GARAGE INTO FAMILY RM & ADD NEW ATTACHED TANDEM CARPORT (9'4" X 32'10"). ALL WORK PER ENGR DESIGN.
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 4/12/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/26/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 5/9/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 5/12/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 5/15/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/18/2021 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 5/18/2021 | APPLICANT |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 10/18/2024 | JEFFREY HARTLINE |
| Permit Finaled | 1/9/2025 | JOHN JANSON |
| CofO Issued | 1/9/2025 | JOHN JANSON |
| Permit Finaled | 1/9/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2021 | ADRIAN CASTRO |
| Permit | Cleared | 4/16/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/16/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Tri Tech Restoration & Construction Co Inc; Lic. No.: 501801-B | 3301 N SAN FERNANDO BLVD BURBANK, CA 91504 |
| Engineer | Chen,, Yeshen Jason; Lic. No.: C40169 | 20601 ALDA CT WALNUT, CA 91789 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/8/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 2/9/2024 | Conditional Approval | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 2/14/2024 | Corrections Issued | JEFFREY HARTLINE |
| Deputy Drilled-In Anchors | 2/27/2024 | Conditional Approval | JEFFREY HARTLINE |
| Deputy Drilled-In Anchors | 2/28/2024 | Conditional Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 2/29/2024 | Partial Approval | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 2/29/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 2/29/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 3/13/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 3/21/2024 | Corrections Issued | MORRIS JACKSON |
| BUILDING-Rough-Frame | 5/9/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 5/9/2024 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 5/9/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 5/9/2024 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/9/2024 | Approved | CHRIS CHRISTENSEN |
| Insulation | 5/15/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/15/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 5/23/2024 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 5/23/2024 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 9/27/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 9/27/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 9/27/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/27/2024 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 10/17/2024 | Approved | JEFFREY HARTLINE |
| Final | 10/17/2024 | OK to Issue CofO | JEFFREY HARTLINE |
| Green Building Final | 10/17/2024 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 10/17/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 10/17/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Special/Order Compliance | 10/29/2024 | Corrections Issued | JEFFREY HARTLINE |