15219-15221 W LEMARSH ST 91345

Certificate Information: 15219-15221 W LEMARSH ST 91345

Application / Permit
21014-20000-01756
Plan Check / Job No.
B21VN04227
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATT. GARAGE TO ADU WITH 2ND STORY ADDITION, (20'-0"x22'-0") 729.79 PER LAMC 12.22 A.33(c)(e)
Permit Issued
Issued on 2/15/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 PETER MOSESIAN
Corrections Issued 5/19/2021 PETER MOSESIAN
Quality Review Completed 6/7/2021 OMID HEDAYAT
Building Plans Picked Up 6/18/2021 APPLICANT
Applicant returned to address corrections 2/15/2022 PETER MOSESIAN
Plan Check Approved 2/6/2023 PETER MOSESIAN
Issued 2/15/2023 APPLICANT
CofO in Progress 8/28/2025 JENNIFER RABUCHIN
Permit Finaled 9/9/2025 RUBEN SALAS
CofO Issued 9/9/2025 RUBEN SALAS
Permit Finaled 9/9/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/21/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/21/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/13/2021 GILBERT URREA
Sewer availability Cleared 1/4/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/10/2022 ROSE MARIE SMITH

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/1/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 7/1/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/11/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/17/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 7/17/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval JENNIFER RABUCHIN
Wood Frame 7/30/2024 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/16/2024 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Partial Approval JENNIFER RABUCHIN
Green Building Rough 8/16/2024 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 8/16/2024 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 8/22/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 9/3/2024 Approved RYAN SALAZAR
PLUMBING-Rough 9/3/2024 Approved RYAN SALAZAR
Insulation 9/5/2024 Approved JEFFREY BULL
Drywall Nailing 9/26/2024 Approved JENNIFER RABUCHIN
Green Building Rough 9/26/2024 Approved JENNIFER RABUCHIN
Shower Pan 9/26/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/19/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/7/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 7/8/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/8/2025 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/28/2025 Approved JENNIFER RABUCHIN
Final 7/28/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 7/28/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/28/2025 Approved JENNIFER RABUCHIN
Final 8/11/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/11/2025 Approved JENNIFER RABUCHIN
Final 8/27/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 8/27/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/27/2025 Approved JENNIFER RABUCHIN