16423 W LAHEY ST 91344
Certificate Information: 16423 W LAHEY ST 91344
- Application / Permit
- 21014-20000-01754
- Plan Check / Job No.
- B21VN04224
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 21' X 20'-6" ADDITION TO (E) SFD FOR NEW BEDROOM AND BATHROOM. WORK PER WFPP.
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- CofO Issued on 9/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | ROSENDO MEDINA |
| Corrections Issued | 4/21/2021 | ROSENDO MEDINA |
| Plan Check Approved | 5/19/2021 | ROSENDO MEDINA |
| Issued | 5/20/2021 | APPLICANT |
| Building Plans Picked Up | 5/20/2021 | APPLICANT |
| CofO in Progress | 8/30/2021 | MARK JOHNSON |
| CofO Issued | 9/18/2021 | MICHAEL SMITH |
| Permit Finaled | 9/18/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/28/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 5/3/2021 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 5/5/2021 | ROSENDO MEDINA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/14/2021 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 7/16/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 7/26/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 7/26/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 7/26/2021 | Approved | MARK JOHNSON |
| Wood Frame | 7/26/2021 | Approved | MARK JOHNSON |
| Insulation | 8/3/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/3/2021 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 8/6/2021 | Approved | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 8/6/2021 | Corrections Issued | MICHAEL TEMPLE |
| Shower Pan | 8/11/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/13/2021 | Approved | MARK JOHNSON |
| Underground Mechanical | 8/13/2021 | Approved | MARK JOHNSON |
| Pre-Inspection | 8/25/2021 | Corrections Issued | MARK JOHNSON |
| BUILDING-Rough-Frame | 8/27/2021 | Approved | MARK JOHNSON |
| Final | 8/27/2021 | Corrections Issued | MARK JOHNSON |
| Footing/Foundation/Slab | 8/27/2021 | Approved | MARK JOHNSON |
| Green Building Final | 8/27/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 8/27/2021 | Approved | MARK JOHNSON |
| MERV13>=Final | 8/27/2021 | Approved | MARK JOHNSON |
| MERV13>=Rough | 8/27/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 8/27/2021 | SGSOV Approved | MARK JOHNSON |
| Smoke Detectors | 8/27/2021 | Approved | MARK JOHNSON |
| Final | 8/31/2021 | OK to Issue CofO | MARK JOHNSON |