14623 W LEADWELL ST 91405

Certificate Information: 14623 W LEADWELL ST 91405

Application / Permit
21014-20000-01752
Plan Check / Job No.
B21VN04217
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d), AND ADDITION OF (26'-2" x 35'-1").
Permit Issued
Issued on 9/8/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 4/14/2021 LUIS RINCON
Corrections Issued 4/17/2021 LUIS RINCON
Building Plans Picked Up 7/20/2021 APPLICANT
Plan Check Approved 8/26/2022 SARKIS HARABEDIAN
Issued 9/8/2022 APPLICANT
CofO in Progress 11/21/2023 GREGG CUMMINGS
Permit Finaled 12/19/2023 RUBEN SALAS
CofO Issued 12/19/2023 RUBEN SALAS
Permit Finaled 12/19/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/4/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/4/2021 GABRIEL ROBLES
Sewer availability Cleared 5/4/2021 GABRIEL ROBLES
Low Impact Development Cleared 10/6/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/7/2021 DAGOVERTO GUERRERO
Permit Cleared 12/13/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 8/26/2022 JOHN BACON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/8/2023 Approved CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 3/23/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 3/28/2023 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 3/30/2023 Conditional Approval CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 3/30/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 3/30/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 4/1/2023 Approved DAVID ANDERSON
Footing/Foundation/Slab 4/1/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 4/13/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/17/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 4/17/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/25/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 4/25/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Pre-Inspection 4/25/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 5/18/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 5/18/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 6/2/2023 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 6/2/2023 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 6/2/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 6/2/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/2/2023 Partial Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/12/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 6/16/2023 Approved DAVID MATSON
ELECTRICAL-Rough 6/16/2023 Approved DAVID MATSON
Interior/Exterior Lathing 6/16/2023 Partial Approval DAVID MATSON
Wood Frame 6/16/2023 Approved DAVID MATSON
Insulation 6/20/2023 Approved WILLIAM WREN
Drywall Nailing 6/23/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 7/13/2023 Partial Approval GREGG CUMMINGS
Shower Pan 7/13/2023 Approved GREGG CUMMINGS
Underground Mechanical 8/14/2023 Approved MATTHEW NELSON
Underground Mechanical 9/20/2023 Partial Approval GREGG CUMMINGS
ELECTRICAL-Final 11/13/2023 Not Ready for Inspection GREGG CUMMINGS
Final 11/13/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 11/13/2023 Approved GREGG CUMMINGS
HVAC-Final 11/13/2023 Approved GREGG CUMMINGS
PLUMBING-Final 11/13/2023 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Approved GREGG CUMMINGS
Service/Power Release 11/13/2023 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 11/13/2023 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 11/20/2023 Approved GREGG CUMMINGS
Final 11/20/2023 OK to Issue CofO GREGG CUMMINGS
PLUMBING-Final 11/20/2023 Approved GREGG CUMMINGS
Smoke Detectors 11/20/2023 Approved GREGG CUMMINGS