7537 N LILLA PL 91304

Certificate Information: 7537 N LILLA PL 91304

Application / Permit
21014-20000-01739
Plan Check / Job No.
B21VN04175
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 16' X 23'-2" ADDITION FOR (N) FAMILY ROOM TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/10/2021
Issuing Office
Valley
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2021 APPLICANT
Assigned to Plan Check Engineer 4/20/2021 RAPHAEL ROSAS
Corrections Issued 4/20/2021 RAPHAEL ROSAS
Plan Check Approved 5/24/2021 RAPHAEL ROSAS
Building Plans Picked Up 5/27/2021 APPLICANT
Issued 6/10/2021 APPLICANT
CofO in Progress 11/1/2023 JEFFREY HARTLINE
Permit Finaled 1/10/2024 JOHN JANSON
CofO Issued 1/10/2024 JOHN JANSON
Permit Finaled 1/10/2024 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/30/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/3/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 5/24/2021 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2022 Partial Approval JEFFREY PARD
Deputy Drilled-In Anchors 4/11/2022 Conditional Approval JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 4/13/2022 Approved CHRIS CHRISTENSEN
Deputy Wood Construction 4/20/2022 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/21/2022 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 4/21/2022 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/25/2022 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 4/25/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/25/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/28/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 4/28/2022 Approved CHRIS CHRISTENSEN
Insulation 4/28/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 5/3/2022 Approved JESUS PINEDA
Final 6/6/2022 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/6/2022 Approved CHRIS CHRISTENSEN
Green Building Final 6/6/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/6/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 6/6/2022 Approved CHRIS CHRISTENSEN
Final 10/31/2023 OK to Issue CofO JEFFREY HARTLINE